1165 E 34TH ST 90011
Certificate Information: 1165 E 34TH ST 90011
- Application / Permit
- 20016-10000-25681
- Plan Check / Job No.
- B20LA18712
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION TO THE REAR (E) SINGLE FAMILY DWELLING. REPLACING EXISTING BEDROOMS WINDOWS WITH NEW WINDOWS THAT MEET EGRESS AT EXISTING BUILDINGS
- Permit Issued
- Issued on 6/17/2021
- Issuing Office
- Current Status
- CofO Issued on 10/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | FERNANDO FLORES |
| Corrections Issued | 10/19/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 12/7/2020 | DANIEL YIP |
| Applicant returned to address corrections | 12/24/2020 | SINA KHOSRAVI |
| Plan Check Approved | 5/25/2021 | RICARDO RAMIREZ |
| Issued | 6/17/2021 | APPLICANT |
| Building Plans Picked Up | 6/23/2021 | APPLICANT |
| CofO in Progress | 10/26/2022 | CHARLES BOGHOSKHAN |
| CofO in Progress | 10/26/2022 | CHARLES BOGHOSKHAN |
| Permit Finaled | 10/26/2022 | DEROLD HAUFF |
| CofO Issued | 10/26/2022 | DEROLD HAUFF |
| Permit Finaled | 10/26/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/14/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2020 | CELINA MORENO |
| Tenant Habitability Plan | Cleared | 4/13/2021 | RICHARD BRINSON |
Contact Information
| Contractor | Viera Design & Construction; Lic. No.: 972064-B | 17646 E BENBOW ST COVINA, CA 91722 |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/22/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Drywall Nailing | 6/22/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 6/22/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/22/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 6/22/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 6/22/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Pre-Inspection | 6/22/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 6/22/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 6/22/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 7/15/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Drywall Nailing | 7/15/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 7/15/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/15/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 7/15/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 7/15/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/15/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 7/15/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 11/18/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 11/18/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 2/2/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Wood Frame | 2/18/2022 | Partial Approval | JUSTIN CURTIS |
| BUILDING-Rough-Frame | 3/29/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 3/29/2022 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/25/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 4/25/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 4/25/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 4/25/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 4/28/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 5/2/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 7/28/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 7/28/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/28/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 7/28/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 7/28/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 8/10/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/10/2022 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/10/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/13/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| Smoke Detectors | 9/13/2022 | Approved | SHAVONNE ESPINOZA |
| Final | 9/16/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Final | 10/12/2022 | OK to Issue CofO | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 10/12/2022 | SGSOV Approved | SHAVONNE ESPINOZA |