7711 N CANOGA AVE 91304
Certificate Information: 7711 N CANOGA AVE 91304
- Application / Permit
- 20016-10000-25675
- Plan Check / Job No.
- B20LA18695
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- THE EXISTING BUILDING IS BEING USED AS AN OFFICE WITH A LOCKER ROOM FOR THE FIELD EMPLOYEES. THE SPACE WILL CONTINUE TO BE USED AS AN OFFICE AND LOCKER ROOM WITH SEVERAL IMPROVEMENTS TO THE EXISTING LOCKER ROOM AND ASSEMBLY ROOM. THE PROPOSED LOCKER ROOM REMODEL WILL CONSIST OF 4,286 S.F.
- Permit Issued
- Issued on 10/29/2021
- Issuing Office
- Current Status
- Issued on 10/29/2021
Permit Application Status History
| Submitted | 10/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | TEODORO DIAZ RODRIGUEZ |
| Disabled Access Plans Picked Up | 11/12/2020 | APPLICANT |
| Corrections Issued | 12/9/2020 | TEODORO DIAZ RODRIGUEZ |
| Quality Review Completed | 12/9/2020 | EUGENE BARBEAU |
| Plan Check Approved | 8/16/2021 | TEODORO DIAZ RODRIGUEZ |
| Issued | 10/29/2021 | APPLICANT |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Cleared | 7/20/2021 | SHINE LIN |
Contact Information
| Contractor | Keoni Gustav; Lic. No.: 1026968-B | 3480 S HIGUERA ST STE 130 SAN LUIS OBISPO, CA 93401 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/3/2021 | Partial Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 1/10/2022 | Conditional Approval | JEFFREY FULTON |
| Footing/Foundation/Slab | 1/10/2022 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 2/16/2022 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 2/16/2022 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 2/25/2022 | Partial Inspection | JEFFREY FULTON |
| Insulation | 3/11/2022 | Approved | JEFFREY FULTON |
| Drywall Nailing | 3/22/2022 | Approved | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 5/13/2022 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 5/25/2022 | Approved | KENNETH ROBERTS |
| Footing/Foundation/Slab | 6/2/2022 | No Access for Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 6/2/2022 | No Access for Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 6/6/2022 | Partial Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 6/7/2022 | No Access for Inspection | JEFFREY FULTON |
| Pre-Inspection | 6/8/2022 | No Access for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 6/9/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 6/23/2022 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 6/23/2022 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 6/23/2022 | Approved | JEFFREY FULTON |
| Final | 8/4/2022 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Approved | JEFFREY FULTON |