1245 N NEPTUNE AVE 90744
Certificate Information: 1245 N NEPTUNE AVE 90744
- Application / Permit
- 20016-10000-25437
- Plan Check / Job No.
- B20LA18532
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(B)(5)
- Permit Issued
- Issued on 1/7/2021
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | MONICA RAMIREZ |
| Corrections Issued | 10/19/2020 | MONICA RAMIREZ |
| Quality Review Completed | 10/27/2020 | TU HUA |
| Applicant returned to address corrections | 11/16/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 11/17/2020 | MONICA RAMIREZ |
| Plan Check Approved | 11/17/2020 | MONICA RAMIREZ |
| No Progress | 11/17/2020 | MONICA RAMIREZ |
| Plan Check Approved | 1/4/2021 | MONICA RAMIREZ |
| No Progress | 1/4/2021 | MONICA RAMIREZ |
| Plan Check Approved | 1/4/2021 | MONICA RAMIREZ |
| Issued | 1/7/2021 | APPLICANT |
| CofO in Progress | 9/29/2022 | EUGENE CASSIDY |
| Permit Finaled | 11/19/2022 | DEROLD HAUFF |
| Permit Finaled | 11/19/2022 | DEROLD HAUFF |
| CofO Issued | 11/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2020 | CHINH DINH |
| Sewer availability | Cleared | 10/21/2020 | CHINH DINH |
Contact Information
| Architect | Belak-Berger,, Charles Peter; Lic. No.: C13657 | 521 W. ROSECRANS AVE. GARDENA, CA 902481514 |
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2021 | Corrections Issued | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2021 | Not Ready for Inspection | JOHN KLARIN |
| Underground Mechanical | 9/13/2021 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/30/2021 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 12/30/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 12/30/2021 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Rough | 12/30/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 12/30/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/6/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 1/6/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 1/6/2022 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/20/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 1/20/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/31/2022 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Rough | 1/31/2022 | Approved | ANSON MAGLASANG |
| Green Building Rough | 1/31/2022 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 1/31/2022 | Approved | ANSON MAGLASANG |
| Special/Order Compliance | 2/2/2022 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 4/25/2022 | Approved | EUGENE CASSIDY |
| Insulation | 4/25/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/25/2022 | Approved | EUGENE CASSIDY |
| Final | 7/20/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/20/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/20/2022 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 7/20/2022 | Approved | EUGENE CASSIDY |
| Final | 8/10/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 8/10/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 9/15/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/15/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 9/28/2022 | Approved | EUGENE CASSIDY |
| Final | 9/28/2022 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 9/28/2022 | Approved | EUGENE CASSIDY |
| HVAC-Final | 9/28/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 9/28/2022 | Approved | EUGENE CASSIDY |