2114-2118 W 57TH ST 90062

Certificate Information: 2114-2118 W 57TH ST 90062

Application / Permit
20016-10000-25358
Plan Check / Job No.
B20LA18460
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT EXISTING ATTACHED GARAGE AND ADDITION TO ATTACHED ACCESSORY DWELLING UNIT AT REAR OF EXISTING DUPLEX PER LAMC 12.22 A.33(c) and (e) ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 4/16/2021
Issuing Office
Current Status
CofO Issued on 3/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 SHANGQIN XIE
Corrections Issued 10/23/2020 SHANGQIN XIE
Applicant returned to address corrections 12/8/2020 GEORGE ALVAREZ
Building Plans Picked Up 4/13/2021 APPLICANT
Issued 4/16/2021 APPLICANT
CofO in Progress 2/24/2022 SABAS ALONSO
Permit Finaled 3/5/2022 DEROLD HAUFF
CofO Issued 3/5/2022 DEROLD HAUFF
Permit Finaled 3/5/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/14/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 12/14/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 12/16/2020 JEANIE LAM
Sewer availability Cleared 12/16/2020 JEANIE LAM
Tenant Habitability Plan Cleared 3/25/2021 RICHARD BRINSON

Contact Information

Contractor Tennex Construction; Lic. No.: 1070554-B 1237 ARMACOST AVE #2      LOS ANGELES, CA 90025

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/25/2021 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 6/25/2021 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/27/2021 Not Ready for Inspection SABAS ALONSO
Excavation/Setback/Form/Re-Bar 9/1/2021 Not Ready for Inspection SABAS ALONSO
Excavation/Setback/Form/Re-Bar 9/14/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 9/14/2021 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 10/8/2021 Approved SABAS ALONSO
ELECTRICAL-Rough 11/18/2021 Corrections Issued SABAS ALONSO
Green Building Rough 11/18/2021 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 12/1/2021 Approved SABAS ALONSO
PLUMBING-Rough 12/1/2021 Approved SABAS ALONSO
Underground Mechanical 12/1/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/6/2021 Approved SABAS ALONSO
ELECTRICAL-Rough 12/6/2021 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Approved SABAS ALONSO
Green Building Rough 12/6/2021 Approved SABAS ALONSO
HVAC-Rough 12/6/2021 Approved SABAS ALONSO
PLUMBING-Rough 12/6/2021 Approved SABAS ALONSO
Insulation 12/9/2021 Partial Approval SHAVONNE ESPINOZA
Insulation 12/14/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 12/14/2021 Approved SABAS ALONSO
Drywall Nailing 12/16/2021 Corrections Issued SHAVONNE ESPINOZA
Drywall Nailing 12/21/2021 Approved SABAS ALONSO
ELECTRICAL-Final 1/27/2022 Not Ready for Inspection HORACE FULTZ
Gas Test 1/27/2022 Not Ready for Inspection HORACE FULTZ
HVAC-Final 1/27/2022 Approved HORACE FULTZ
PLUMBING-Final 1/27/2022 Approved HORACE FULTZ
Service/Power Release 1/27/2022 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Final 2/7/2022 Not Ready for Inspection SABAS ALONSO
Gas Test 2/7/2022 Approved SABAS ALONSO
Service/Power Release 2/7/2022 Approved SABAS ALONSO
ELECTRICAL-Final 2/18/2022 Approved SABAS ALONSO
Final 2/18/2022 Corrections Issued SABAS ALONSO
Final 2/25/2022 OK to Issue CofO SABAS ALONSO
Green Building Final 2/25/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Approved SABAS ALONSO
Smoke Detectors 2/25/2022 Approved SABAS ALONSO
Service/Power Release 3/4/2022 Approved SABAS ALONSO