1241 S SOTO ST 90023

Certificate Information: 1241 S SOTO ST 90023

Application / Permit
20016-10000-25287
Plan Check / Job No.
B20LA18423
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) Private School
Work Description
PARTIAL INTERIOR TI OF AN (E) SCHOOL BUILDING. AREA OF WORK @ 1ST FLOOR 14,623 SF & 2ND FLOOR 21,357 SF NO EXPANSION OF EXISTING BUILDING
Permit Issued
Issued on 5/25/2021
Issuing Office
Current Status
Permit Finaled on 7/26/2022

Permit Application Status History

Submitted 10/8/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 GARO TELMI
Corrections Issued 10/21/2020 GARO TELMI
Quality Review Completed 10/22/2020 CHAD DOI
Disabled Access Plans Picked Up 11/12/2020 APPLICANT
Applicant returned to address corrections 1/7/2021 GARO TELMI
Applicant returned to address corrections 1/12/2021 GARO TELMI
Green Plans Picked Up 4/19/2021 APPLICANT
Plan Check Approved 5/12/2021 GARO TELMI
Issued 5/25/2021 APPLICANT
Building Plans Picked Up 5/27/2021 APPLICANT
Permit Finaled-Status Void 11/15/2021 DANIEL COLLINS
Re-Activate Permit 7/15/2022 DANIEL COLLINS
Permit Finaled 7/26/2022 MARK FERRARI

Permit Application Clearance Information

Clean Up Green Up Cleared 12/4/2020 ANACANY HURTADO
Redevelopment Project Area Cleared 12/18/2020 GRACIELA ACOSTA
Green Code Cleared 1/5/2021 GARO TELMI
DAS Clearance Cleared 2/4/2021 GARO TELMI
Fire Marshal Fire Life Safety Cleared 5/5/2021 MENOA AGHAJANI

Contact Information

Architect Wang,, Johann D; Lic. No.: C27010 3375 CANTON WAY      STUDIO CITY, CA 91604
Contractor E P I Construction Inc; Lic. No.: 865616-B 12345 VENTURA BLVD SUITE H      STUDIO CITY, CA 91604
Engineer Baroonian,, Armen; Lic. No.: S4227 867 N FAIR OAKS AVE 100      PASADENA, CA 91103

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 6/24/2021 Not Ready for Inspection LANNY MERRICK
Footing/Foundation/Slab 7/6/2021 Partial Approval MARK FERRARI
Drywall Nailing 7/21/2021 Partial Approval LANNY MERRICK
Light Gage Steel Frame 7/21/2021 Corrections Issued LANNY MERRICK
Drywall Nailing 7/27/2021 Partial Approval LANNY MERRICK
Insulation 7/27/2021 Partial Approval LANNY MERRICK
Drywall Nailing 8/2/2021 Partial Approval DAVID TSAU
Insulation 8/2/2021 Partial Approval DAVID TSAU
Drywall Nailing 8/6/2021 Approved LANNY MERRICK
Drywall Nailing 8/12/2021 Partial Approval LANNY MERRICK
Drywall Nailing 8/20/2021 Partial Approval LANNY MERRICK
Special/Order Compliance 8/25/2021 Corrections Issued LANNY MERRICK
Insulation 9/13/2021 Partial Approval DANIEL COLLINS
Deputy Drilled-In Anchors 9/17/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Masonry 9/17/2021 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 9/24/2021 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 9/29/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 9/29/2021 Conditional Approval DANIEL COLLINS
T-Bar Ceiling 9/29/2021 Partial Approval MARK FERRARI
T-Bar Ceiling 10/18/2021 Conditional Approval DANIEL COLLINS
Final 11/10/2021 Conditional Approval DANIEL COLLINS
Green Building Final 11/10/2021 Approved DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 11/10/2021 SGSOV Approved DANIEL COLLINS
Smoke Detectors 11/10/2021 Approved DANIEL COLLINS
Final 11/15/2021 Partial Inspection DANIEL COLLINS
Final 7/26/2022 Permit Finaled MARK FERRARI