11017 W HORTENSE ST 91403

Certificate Information: 11017 W HORTENSE ST 91403

Application / Permit
20016-10000-25220
Plan Check / Job No.
B20LA18373
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert existing accessory building to detached ADU per state law GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 11/25/2020
Issuing Office
Current Status
CofO Issued on 7/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2020 APPLICANT
Assigned to Plan Check Engineer 10/21/2020 HELEN NGUYEN
Corrections Issued 10/21/2020 HELEN NGUYEN
Quality Review Completed 10/27/2020 MINYE PAK
Plan Check Approved 11/20/2020 CARLOS MONTES
Issued 11/25/2020 APPLICANT
CofO in Progress 11/22/2021 THOMAS FINNILA
Permit Finaled 7/28/2022 MICHAEL SMITH
CofO Issued 7/28/2022 MICHAEL SMITH
Permit Finaled 7/28/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/28/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/28/2020 GABRIEL ROBLES
Sewer availability Cleared 10/28/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2021 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 2/25/2021 Approved THOMAS FINNILA
PLUMBING-Rough 3/5/2021 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 3/26/2021 Partial Approval THOMAS FINNILA
PLUMBING-Rough 3/26/2021 Partial Approval THOMAS FINNILA
PLUMBING-Rough 4/20/2021 Approved THOMAS FINNILA
ELECTRICAL-Rough 4/21/2021 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 5/4/2021 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 5/4/2021 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 5/4/2021 Approved THOMAS FINNILA
ELECTRICAL-Rough 5/5/2021 Approved THOMAS FINNILA
HVAC-Rough 5/5/2021 Conditional Approval THOMAS FINNILA
Interior/Exterior Lathing 5/25/2021 Corrections Issued DEANDRE HOFFMAN
BUILDING-Rough-Frame 5/28/2021 Approved THOMAS FINNILA
Green Building Rough 5/28/2021 Approved THOMAS FINNILA
HVAC-Rough 5/28/2021 Approved THOMAS FINNILA
Insulation 6/1/2021 Approved MORRIS JACKSON
Drywall Nailing 6/16/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 6/28/2021 Partial Approval JAVIER RAMOS JR
Shower Pan 6/29/2021 Approved ALAN MORELOS
ELECTRICAL-Final 10/21/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Final 10/21/2021 Approved THOMAS FINNILA
Final 10/22/2021 Corrections Issued THOMAS FINNILA
Green Building Final 10/22/2021 Corrections Issued THOMAS FINNILA
ELECTRICAL-Final 11/9/2021 Approved THOMAS FINNILA
MERV13>=Final 11/9/2021 Approved THOMAS FINNILA
Final 11/16/2021 Partial Inspection THOMAS FINNILA
Green Building Final 11/16/2021 Partial Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 11/16/2021 SGSOV Approved THOMAS FINNILA
Smoke Detectors 11/16/2021 Approved THOMAS FINNILA
HVAC-Final 11/17/2021 Approved THOMAS FINNILA
Final 11/22/2021 OK to Issue CofO THOMAS FINNILA
Green Building Final 11/22/2021 Approved THOMAS FINNILA