22529-22531 W MARLIN PL 91307
Certificate Information: 22529-22531 W MARLIN PL 91307
- Application / Permit
- 20016-10000-25064
- Plan Check / Job No.
- B20LA18308
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert exisitng atached garage 22.5x20.75 into an accessory dwelling unit per state law GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/21/2020
- Issuing Office
- Current Status
- CofO Issued on 9/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | VU NGUYEN |
| Corrections Issued | 10/22/2020 | VU NGUYEN |
| Quality Review Completed | 10/28/2020 | MINYE PAK |
| Applicant returned to address corrections | 11/30/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 12/2/2020 | ARSALAN SHABESTARI |
| Plan Check Approved | 12/15/2020 | CARLOS MONTES |
| Issued | 12/21/2020 | APPLICANT |
| CofO in Progress | 9/29/2021 | TROY SANDERS |
| Permit Finaled | 9/13/2022 | DANIEL ORRANTE |
| CofO Issued | 9/13/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/13/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/10/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 11/10/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Teamwork Remodeling Group; Lic. No.: 1036884-B | 22122 SHERMAN WAY UNIT 303 CANOGA PARK, CA 91303 |
| Engineer | Chaaya,, Danny Camille; Lic. No.: NA45555 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/28/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 6/1/2021 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 6/1/2021 | Not Ready for Inspection | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 6/1/2021 | Corrections Issued | TROY SANDERS |
| BUILDING-Rough-Frame | 6/8/2021 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 6/8/2021 | Approved | TROY SANDERS |
| HVAC-Rough | 6/8/2021 | Corrections Issued | TROY SANDERS |
| PLUMBING-Rough | 6/8/2021 | Approved | TROY SANDERS |
| Insulation | 6/18/2021 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 6/21/2021 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 6/30/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 7/7/2021 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 7/7/2021 | Not Ready for Inspection | STEPHANIE SWANSON |
| Drywall Nailing | 7/9/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 7/9/2021 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 7/9/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 7/13/2021 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 7/13/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Drywall Nailing | 7/27/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| Interior/Exterior Lathing | 7/27/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| Drywall Nailing | 8/2/2021 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/2/2021 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 8/12/2021 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 8/16/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/18/2021 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/20/2021 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 9/15/2021 | Not Ready for Inspection | TROY SANDERS |
| Final | 9/15/2021 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 9/15/2021 | Not Ready for Inspection | TROY SANDERS |
| Green Building Rough | 9/15/2021 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/15/2021 | SGSOV Not Ready | TROY SANDERS |
| Smoke Detectors | 9/15/2021 | No Access for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 9/21/2021 | Approved | TROY SANDERS |
| Final | 9/21/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 9/21/2021 | Corrections Issued | TROY SANDERS |
| Green Building Rough | 9/21/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/21/2021 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 9/21/2021 | Approved | TROY SANDERS |
| Final | 9/29/2021 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 9/29/2021 | Approved | TROY SANDERS |
| Service/Power Release | 9/29/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 11/1/2021 | Approved | TROY SANDERS |