121 S UNION PL 90026
Certificate Information: 121 S UNION PL 90026
- Application / Permit
- 20016-10000-24979
- Plan Check / Job No.
- B20LA18259
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE GARAGE PORTION OF AN EXISTING DETACHED GARAGE AND LAUNDRY ROOM INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 2/3/2021
- Issuing Office
- Current Status
- CofO Issued on 9/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2020 | STANLEY RAAP |
| Corrections Issued | 10/26/2020 | STANLEY RAAP |
| Building Plans Picked Up | 11/10/2020 | APPLICANT |
| Applicant returned to address corrections | 12/15/2020 | LUKE GONZALES |
| Plan Check Approved | 2/1/2021 | LUKE GONZALES |
| Plan Check Approved | 2/2/2021 | LUKE GONZALES |
| Plan Check Approved | 2/2/2021 | LUKE GONZALES |
| Issued | 2/3/2021 | APPLICANT |
| CofO in Progress | 8/16/2022 | THOMAS LOGRASSO |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
| CofO Issued | 9/16/2022 | DEROLD HAUFF |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 11/30/2020 | GRACIELA ACOSTA |
| ZI | Cleared | 11/30/2020 | GRACIELA ACOSTA |
| Hydrant and Access approval | Cleared | 12/7/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 12/10/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2020 | CELINA MORENO |
| Sewer availability | Cleared | 12/10/2020 | CELINA MORENO |
| Abandoned oil well | Cleared | 1/19/2021 | KURT CORRAL |
| ZI | Cleared | 1/19/2021 | MAXFIELD VERMY |
Contact Information
| Contractor | Tennex Construction; Lic. No.: 1070554-B | 1237 ARMACOST AVE #2 LOS ANGELES, CA 90025 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/23/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 6/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 6/1/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Rough | 6/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Rough | 6/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 6/22/2021 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2021 | Partial Approval | ROBERT VORHIS |
| PLUMBING-Rough | 6/22/2021 | Not Ready for Inspection | ROBERT VORHIS |
| BUILDING-Rough-Frame | 7/8/2021 | Not Ready for Inspection | RUBEN SALAS |
| Green Building Rough | 7/8/2021 | Not Ready for Inspection | RUBEN SALAS |
| METHANE-Rough | 7/8/2021 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 7/8/2021 | Partial Approval | RUBEN SALAS |
| Wood Frame | 7/8/2021 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 7/15/2021 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 7/15/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/6/2021 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/9/2021 | No Access for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2021 | No Access for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 11/9/2021 | No Access for Inspection | THOMAS LOGRASSO |
| METHANE-Rough | 11/9/2021 | No Access for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/16/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2021 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 11/16/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| METHANE-Rough | 11/16/2021 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/30/2021 | Partial Approval | JOSE AVILA |
| Green Building Rough | 11/30/2021 | Corrections Issued | JOSE AVILA |
| METHANE-Rough | 11/30/2021 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 12/6/2021 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 12/6/2021 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 12/7/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 12/9/2021 | Partial Approval | RUBEN SALAS |
| Insulation | 12/14/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/17/2021 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 12/17/2021 | Approved | THOMAS LOGRASSO |
| Insulation | 12/17/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/17/2021 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 3/1/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 8/8/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 8/8/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 8/8/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 8/8/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 8/8/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/8/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 8/8/2022 | Approved | THOMAS LOGRASSO |
| Final | 8/15/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 8/15/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Approved | THOMAS LOGRASSO |