13954 W VAN NUYS BLVD 91331

Certificate Information: 13954 W VAN NUYS BLVD 91331

Application / Permit
20016-10000-24863
Plan Check / Job No.
B20LA18174
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE OF USE TO RESTAURANT AND TI FOR DONUT SHOP.
Permit Issued
Issued on 7/28/2021
Issuing Office
Current Status
CofO Issued on 5/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 JOE VO
Corrections Issued 12/13/2020 JOE VO
Quality Review Completed 12/24/2020 MINYE PAK
Applicant returned to address corrections 6/8/2021 JOE VO
Plan Check Approved 7/6/2021 JOE VO
Issued 7/28/2021 APPLICANT
Building Plans Picked Up 8/7/2021 APPLICANT
CofO in Progress 5/11/2023 CAMERON CHABAN
Permit Finaled 5/16/2023 JEFFREY DURAN
CofO Issued 5/16/2023 JEFFREY DURAN
Permit Finaled 5/16/2023 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/14/2021 GABRIEL ROBLES
"Q" conditions Cleared 2/8/2021 RUBEN VASQUEZ
Sewer availability Cleared 2/18/2021 MARKOS PEREZ-BRAN
Food Service Establishment Cleared 3/23/2021 JASH PATEL
Automotive Use Cleared 4/7/2021 RUBEN VASQUEZ
Automotive Use Cleared 4/7/2021 RUBEN VASQUEZ
Automotive Use Cleared 4/7/2021 RUBEN VASQUEZ
Food establishment approval Cleared 4/8/2021 LACDHS APPROVED
DAS Clearance Cleared 5/16/2021 ELIZABETH TOMS

Contact Information

Contractor Heinemeyer Michael M; Lic. No.: 726373-B PO BOX 519#      CEDAR GLEN, CA 92321

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/25/2022 Approved ANDREW DORSO
Wood Frame 5/25/2022 Corrections Issued ANDREW DORSO
Light Gage Steel Frame 8/9/2022 Approved ANDREW DORSO
Drywall Nailing 8/17/2022 Approved ANDREW DORSO
Excavation/Setback/Form/Re-Bar 11/21/2022 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 11/21/2022 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 11/29/2022 No Access for Inspection DANIEL VARNUM
Masonry Wall/Backfill 11/29/2022 Approved DANIEL VARNUM
T-Bar Ceiling 1/13/2023 Approved ANDREW DORSO
Final 4/20/2023 Partial Inspection CAMERON CHABAN
METHANE-Final 4/20/2023 Partial Inspection CAMERON CHABAN
METHANE-Rough 4/20/2023 Conditional Approval CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 4/20/2023 SGSOV Approved CAMERON CHABAN
Smoke Detectors 4/20/2023 Approved CAMERON CHABAN
Wood Frame 4/20/2023 Conditional Approval CAMERON CHABAN
Final 4/27/2023 Partial Inspection CAMERON CHABAN
METHANE-Final 4/27/2023 Approved CAMERON CHABAN
METHANE-Rough 4/27/2023 Approved CAMERON CHABAN
Wood Frame 4/27/2023 Approved CAMERON CHABAN
Final 5/11/2023 OK to Issue CofO CAMERON CHABAN