14 E LIGHTHOUSE ST 90292
Certificate Information: 14 E LIGHTHOUSE ST 90292
- Application / Permit
- 20016-10000-24817
- Plan Check / Job No.
- B20LA18147
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT AN EXISTING 689.28 SQ FT unpermitted GUEST ROOM INTO AN ADU. THE ADU WILL BE DESIGNATED AS UNIT 1. SEE COMMENTS
- Permit Issued
- Issued on 12/17/2020
- Issuing Office
- Current Status
- CofO Issued on 5/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 10/14/2020 | SERGIO GUTIERREZ |
| Disabled Access Plans Picked Up | 10/16/2020 | APPLICANT |
| Quality Review Completed | 10/22/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 10/22/2020 | APPLICANT |
| Plan Check Approved | 12/3/2020 | SERGIO GUTIERREZ |
| Issued | 12/17/2020 | APPLICANT |
| CofO in Progress | 4/27/2021 | GRANT WOODS |
| Permit Finaled | 5/7/2021 | TED RIES |
| CofO Issued | 5/7/2021 | TED RIES |
| Permit Finaled | 5/7/2021 | TED RIES |
Permit Application Clearance Information
| DAS Clearance | Cleared | 10/19/2020 | SHINE LIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2020 | NIKTA MOUSAVI |
| Address approval | Cleared | 10/23/2020 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 10/23/2020 | NIKTA MOUSAVI |
| Specific Plan | Cleared | 11/5/2020 | PEDRO AYALA |
| Specific Plan | Cleared | 11/5/2020 | PEDRO AYALA |
| Coastal Zone | Cleared | 11/10/2020 | NOAH MCCOY |
| Specific Plan | Cleared | 11/10/2020 | NOAH MCCOY |
| Specific Plan | Cleared | 11/10/2020 | NOAH MCCOY |
| Tenant Habitability Plan | Cleared | 11/16/2020 | MICHAEL GREGERSON |
Contact Information
| Engineer | Sims,, Bradley Alan; Lic. No.: C58238 | 5462 WINDWARD AVE LONG BEACH, CA 90814 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/13/2021 | Partial Inspection | SORIN CIRSTOIU |
| Final | 4/16/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| METHANE-Final | 4/16/2021 | Approved | LEOPOLDO MENDOZA |
| METHANE-Rough | 4/16/2021 | Approved | LEOPOLDO MENDOZA |
| Smoke Detectors | 4/16/2021 | Approved | LEOPOLDO MENDOZA |
| Wood Frame | 4/16/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 4/27/2021 | OK to Issue CofO | GRANT WOODS |