1115 W 64TH ST 90044
Certificate Information: 1115 W 64TH ST 90044
- Application / Permit
- 20016-10000-24800
- Plan Check / Job No.
- B20LA18137
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. Garage conversion to ADU
- Permit Issued
- Issued on 12/16/2020
- Issuing Office
- Current Status
- CofO Issued on 2/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | ZAW HAN |
| Corrections Issued | 10/27/2020 | ZAW HAN |
| Plan Check Approved | 12/10/2020 | CARLOS MONTES |
| Issued | 12/16/2020 | APPLICANT |
| CofO in Progress | 2/24/2022 | FREDDIE RIVERA |
| Permit Finaled | 2/18/2023 | DANIEL ORRANTE |
| CofO Issued | 2/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 11/24/2020 | PHILLIP MUNGUIA |
| Address approval | Cleared | 12/1/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 12/1/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 12/1/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2020 | RENZ SORIANO |
Contact Information
| Contractor | Moreno General Services Inc; Lic. No.: 879426-B | 14340 ELSWORTH STREET STE 103 MORENO VALLEY, CA 92553 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/1/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 3/1/2021 | Partial Approval | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 3/4/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 3/8/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 8/11/2021 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 8/11/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 8/11/2021 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 8/16/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/16/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 8/16/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 8/16/2021 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 8/18/2021 | Partial Approval | FREDDIE RIVERA |
| Insulation | 9/1/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 9/9/2021 | Approved | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/6/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 12/27/2021 | SGSOV Not Ready | HORACE FULTZ |
| Final | 1/4/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 1/4/2022 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/4/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 1/4/2022 | Approved | FREDDIE RIVERA |
| Final | 1/20/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 1/20/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Final | 1/28/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 1/28/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/28/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 2/7/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 2/7/2022 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Approved | FREDDIE RIVERA |
| Final | 2/22/2022 | Conditional Approval | FREDDIE RIVERA |