1360 S WESTWOOD BLVD 90024

Certificate Information: 1360 S WESTWOOD BLVD 90024

Application / Permit
20016-10000-24699
Plan Check / Job No.
B20LA18069
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Grocery Store
Work Description
T.I & CHANGE OF USE OF OF (E) 2 STORY RETAIL TO GROCERY STORE & RESTAURANT.
Permit Issued
Issued on 10/6/2021
Issuing Office
Valley
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 GARO TELMI
Corrections Issued 12/9/2020 GARO TELMI
Quality Review Completed 12/12/2020 PETER KIM
Building Plans Picked Up 12/17/2020 APPLICANT
Plan Check Approved 9/29/2021 GARO TELMI
Issued 10/6/2021 APPLICANT
TCO Issued (Expire Date: 04-21-2024) 10/24/2023 DAVID TSAU
CofO in Progress 3/28/2024 PAUL DAVIDSON
Permit Finaled 3/29/2024 DAVID TSAU
CofO Issued 3/29/2024 DAVID TSAU
Permit Finaled 3/29/2024 DAVID TSAU

Permit Application Clearance Information

Specific Plan Cleared 1/15/2021 PEDRO AYALA
Miscellaneous Cleared 5/4/2021 DYLAN SITTIG
Supp. Use District POD/CDO/TDO Cleared 5/4/2021 DYLAN SITTIG
ZI Cleared 5/4/2021 DYLAN SITTIG
Green Code Cleared 5/13/2021 AARON COSTA
ZA Case Cleared 5/13/2021 NAOMI GUTH
Eng Process Fee Ord 176,300 Cleared 5/17/2021 RAYMOND MUGAMBWA
ZA Case Cleared 6/1/2021 NAOMI GUTH
Sewer availability Cleared 6/9/2021 RAYMOND MUGAMBWA
Comm Cor/Mini-Mall Cleared 8/13/2021 ANACANY HURTADO
Comm Cor/Mini-Mall Cleared 8/27/2021 ANACANY HURTADO
Fire Marshal Fire Life Safety Cleared 9/12/2021 ANDREW KO
DAS Clearance Cleared 9/16/2021 GARO TELMI
Food establishment approval Cleared 9/24/2021 LACDHS APPROVED
Food Service Establishment Cleared 9/27/2021 KENNETH BROWNE

Contact Information

Architect Budetti,, Robert Peter; Lic. No.: C23757 601 N CEDROS AVE      SOLANO BEACH, CA 92075
Contractor Andres Construction; Lic. No.: 811901-B 663 AZARA PLACE      SUNNYVALE, CA 94086
Engineer Bushra,, Rafeek L; Lic. No.: S4490 2564 W WOODLAND DR      ANAHEIM, CA 92801

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 12/10/2021 Partial Inspection PAUL DAVIDSON
Light Gage Steel Frame 1/4/2022 Partial Approval PAUL DAVIDSON
Structural Steel Frame 1/4/2022 Not Ready for Inspection PAUL DAVIDSON
Insulation 1/11/2022 Partial Approval PAUL DAVIDSON
Structural Steel Frame 1/11/2022 Partial Inspection PAUL DAVIDSON
Drywall Nailing 1/19/2022 Partial Approval PAUL DAVIDSON
Drywall Nailing 1/31/2022 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 1/31/2022 Not Ready for Inspection PAUL DAVIDSON
Structural Steel Frame 1/31/2022 Partial Approval PAUL DAVIDSON
Drywall Nailing 2/8/2022 Partial Approval PAUL DAVIDSON
Insulation 2/8/2022 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 2/8/2022 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 2/15/2022 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 2/25/2022 Partial Approval PAUL DAVIDSON
Drywall Nailing 3/9/2022 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 3/18/2022 Partial Approval PAUL DAVIDSON
Deputy Reinf. Concrete 3/22/2022 Conditional Approval PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 4/11/2022 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 4/11/2022 Partial Approval PAUL DAVIDSON
Insulation 4/14/2022 Partial Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 4/20/2022 Conditional Approval PAUL DAVIDSON
Drywall Nailing 4/20/2022 Partial Approval PAUL DAVIDSON
Footing/Foundation/Slab 4/22/2022 Partial Approval PAUL DAVIDSON
Deputy Reinf. Concrete 4/26/2022 Conditional Approval PAUL DAVIDSON
Deputy Reinf. Concrete 5/4/2022 Conditional Approval PAUL DAVIDSON
Light Gage Steel Frame 5/9/2022 Partial Approval PAUL DAVIDSON
Insulation 5/16/2022 Not Ready for Inspection PAUL DAVIDSON
Structural Steel Frame 5/16/2022 Partial Approval PAUL DAVIDSON
Deputy Steel/Welding 5/18/2022 Conditional Approval PAUL DAVIDSON
Light Gage Steel Frame 5/18/2022 Partial Approval PAUL DAVIDSON
Structural Steel Frame 5/18/2022 Approved PAUL DAVIDSON
Deputy Steel/Welding 5/19/2022 Conditional Approval PAUL DAVIDSON
Drywall Nailing 6/6/2022 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 6/6/2022 Partial Approval PAUL DAVIDSON
Insulation 6/8/2022 Approved PAUL DAVIDSON
Light Gage Steel Frame 6/8/2022 Partial Approval PAUL DAVIDSON
Drywall Nailing 6/13/2022 Not Ready for Inspection PAUL DAVIDSON
Drywall Nailing 6/16/2022 Approved PAUL DAVIDSON
Interior/Exterior Lathing 6/16/2022 Not Ready for Inspection PAUL DAVIDSON
Drywall Nailing 6/27/2022 Partial Inspection PAUL DAVIDSON
Light Gage Steel Frame 6/27/2022 Partial Approval PAUL DAVIDSON
Drywall Nailing 6/30/2022 Approved DERRICK SPENCER
T-Bar Ceiling 7/11/2022 Partial Inspection SORIN CIRSTOIU
Interior/Exterior Lathing 7/13/2022 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 7/14/2022 Partial Approval DERRICK SPENCER
T-Bar Ceiling 7/19/2022 Conditional Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 8/1/2022 Conditional Approval PAUL DAVIDSON
Drywall Nailing 8/5/2022 Approved PAUL DAVIDSON
Light Gage Steel Frame 8/9/2022 Partial Approval PAUL DAVIDSON
Drywall Nailing 8/15/2022 Approved PAUL DAVIDSON
Light Gage Steel Frame 8/15/2022 Partial Approval PAUL DAVIDSON
T-Bar Ceiling 8/18/2022 Approved PAUL DAVIDSON
Drywall Nailing 9/9/2022 Approved PAUL DAVIDSON
Deputy Drilled-In Anchors 9/27/2022 Conditional Approval PAUL DAVIDSON
Special/Order Compliance 10/24/2022 Partial Inspection PAUL DAVIDSON
Green Building Final 11/2/2022 Not Ready for Inspection PAUL DAVIDSON
Green Building Rough 11/2/2022 Approved PAUL DAVIDSON
Reinforced Concrete Frame 11/2/2022 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 11/2/2022 SGSOV Approved PAUL DAVIDSON
Smoke Detectors 11/2/2022 Not Ready for Inspection PAUL DAVIDSON
Special/Order Compliance 11/2/2022 Corrections Issued PAUL DAVIDSON
Special/Order Compliance 11/28/2022 Partial Inspection PAUL DAVIDSON
Special/Order Compliance 2/9/2023 Partial Inspection PAUL DAVIDSON
Special/Order Compliance 2/13/2023 Corrections Issued PAUL DAVIDSON
Green Building Final 8/4/2023 Not Ready for Inspection PAUL DAVIDSON
Pre-Inspection 8/4/2023 Partial Approval PAUL DAVIDSON
Smoke Detectors 8/4/2023 Not Ready for Inspection PAUL DAVIDSON
Final 10/3/2023 Not Ready for Inspection PAUL DAVIDSON
Green Building Final 10/3/2023 Approved PAUL DAVIDSON
Smoke Detectors 10/3/2023 Approved PAUL DAVIDSON
Final 10/17/2023 Not Ready for Inspection PAUL DAVIDSON
Final 10/24/2023 OK for TCO PAUL DAVIDSON
Special/Order Compliance 3/27/2024 Not Ready for Inspection MICHAEL PETRUSKO
Final 3/28/2024 OK to Issue CofO PAUL DAVIDSON