8211 1/2 S HALLDALE AVE 90047
Certificate Information: 8211 1/2 S HALLDALE AVE 90047
- Application / Permit
- 20016-10000-24654
- Plan Check / Job No.
- B20LA18020
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 3/1/2021
- Issuing Office
- Current Status
- CofO Issued on 2/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2020 | LUKE GONZALES |
| Corrections Issued | 10/5/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 1/21/2021 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 2/10/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 2/18/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 3/1/2021 | GEORGE ALVAREZ |
| Issued | 3/1/2021 | APPLICANT |
| Building Plans Picked Up | 3/12/2021 | APPLICANT |
| CofO in Progress | 12/9/2021 | HORACE FULTZ |
| Permit Finaled | 2/2/2022 | DEROLD HAUFF |
| CofO Issued | 2/2/2022 | DEROLD HAUFF |
| Permit Finaled | 2/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2020 | WALLIE JONG |
| Sewer availability | Cleared | 11/20/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 4/27/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/7/2021 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/18/2021 | Conditional Approval | EUGENE CASSIDY |
| Sewer | 5/28/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Sewer | 6/22/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 6/25/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 7/21/2021 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Rough | 7/21/2021 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Rough | 8/18/2021 | Partial Inspection | DAVID FEILER |
| PLUMBING-Rough | 8/18/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 8/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 8/20/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/24/2021 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2021 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 8/24/2021 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/27/2021 | Not Ready for Inspection | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Rough | 8/27/2021 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Rough | 9/9/2021 | Corrections Issued | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2021 | Partial Approval | HORACE FULTZ |
| PLUMBING-Rough | 9/9/2021 | Approved | HORACE FULTZ |
| Shower Pan | 9/9/2021 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 9/17/2021 | Corrections Issued | HORACE FULTZ |
| Interior/Exterior Lathing | 9/23/2021 | Corrections Issued | DAVID FEILER |
| Drywall Nailing | 9/27/2021 | Approved | HORACE FULTZ |
| Insulation | 9/27/2021 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 9/27/2021 | Partial Approval | HORACE FULTZ |
| Drywall Nailing | 9/30/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 9/30/2021 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 10/12/2021 | Partial Approval | HORACE FULTZ |
| Interior/Exterior Lathing | 10/20/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 11/4/2021 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 11/8/2021 | Approved | HORACE FULTZ |
| Final | 11/8/2021 | Corrections Issued | HORACE FULTZ |
| Green Building Final | 11/8/2021 | Approved | HORACE FULTZ |
| Green Building Rough | 11/8/2021 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 11/8/2021 | SGSOV Not Ready | HORACE FULTZ |
| Smoke Detectors | 11/8/2021 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 12/3/2021 | Approved | HORACE FULTZ |
| Final | 12/3/2021 | Conditional Approval | HORACE FULTZ |
| HVAC-Final | 12/3/2021 | Approved | HORACE FULTZ |
| PLUMBING-Final | 12/3/2021 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 12/3/2021 | SGSOV Approved | HORACE FULTZ |
| Final | 12/9/2021 | OK to Issue CofO | HORACE FULTZ |
| Service/Power Release | 12/9/2021 | Approved | HORACE FULTZ |