6955 N GARDEN GROVE AVE 91335

Certificate Information: 6955 N GARDEN GROVE AVE 91335

Application / Permit
20016-10000-24638
Plan Check / Job No.
B20LA17994
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CHANGE EXISTING GARAGE TO ADU.
Permit Issued
Issued on 5/5/2021
Issuing Office
Current Status
CofO Issued on 8/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2020 APPLICANT
Assigned to Plan Check Engineer 10/5/2020 RICARDO RAMIREZ
Corrections Issued 10/6/2020 RICARDO RAMIREZ
Applicant returned to address corrections 12/29/2020 TSE MING HUANG
Applicant returned to address corrections 3/12/2021 SAMUEL GONZALEZ
Building Plans Picked Up 4/1/2021 APPLICANT
Plan Check Approved 4/12/2021 ADAM HEGAZI
Issued 5/5/2021 APPLICANT
CofO in Progress 8/24/2021 MICHAEL SMITH
CofO Issued 8/24/2021 MICHAEL SMITH
Permit Finaled 8/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/1/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/1/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/7/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 3/3/2021 JOHN CONNEALLY

Contact Information

Contractor Royal Home Builders Inc; Lic. No.: 607619-B 18341 SHERMAN WAY #207      RRESEDA, CA 91335

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/14/2021 Corrections Issued JEFFREY PARD
PLUMBING-Rough 5/14/2021 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 5/19/2021 Approved VINCENT HANLEY
PLUMBING-Rough 5/19/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 5/21/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 6/4/2021 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 6/4/2021 Approved PETER FOLLING
HVAC-Rough 6/4/2021 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 6/4/2021 Approved PETER FOLLING
BUILDING-Rough-Frame 6/10/2021 Partial Approval VINCENT HANLEY
HVAC-Rough 6/10/2021 Approved VINCENT HANLEY
Underground Mechanical 6/10/2021 Partial Approval VINCENT HANLEY
Insulation 6/18/2021 Corrections Issued RYAN SALAZAR
Interior/Exterior Lathing 6/18/2021 Approved RYAN SALAZAR
Insulation 6/23/2021 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 6/30/2021 Approved VINCENT HANLEY
Drywall Nailing 7/2/2021 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 8/20/2021 Approved VINCENT HANLEY
Final 8/20/2021 Not Ready for Inspection VINCENT HANLEY
Gas Test 8/20/2021 Approved VINCENT HANLEY
Green Building Final 8/20/2021 Approved VINCENT HANLEY
HVAC-Final 8/20/2021 Approved VINCENT HANLEY
PLUMBING-Final 8/20/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/20/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 8/20/2021 Approved VINCENT HANLEY
Final 8/24/2021 OK to Issue CofO MICHAEL SMITH