3116 W LARGA AVE 90039

Certificate Information: 3116 W LARGA AVE 90039

Application / Permit
20016-10000-24627
Plan Check / Job No.
B20LA17978
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF SFD.RECONFIGURE OF FLOOR PLAN, BATH REMODEL, KITCHEN REMODEL, VAULT CEILING IN LIVING AREA, NEW WINDOWS AND DOORS 1 OF 4
Permit Issued
Issued on 8/26/2021
Issuing Office
Current Status
Permit Finaled on 5/16/2023

Permit Application Status History

Submitted 11/10/2020 APPLICANT
Assigned to Plan Check Engineer 11/26/2020 ARSALAN SHABESTARI
Corrections Issued 11/28/2020 ARSALAN SHABESTARI
Quality Review Completed 12/22/2020 PRANITA SHAH
Building Plans Picked Up 12/30/2020 APPLICANT
Applicant returned to address corrections 4/6/2021 ARSALAN SHABESTARI
Plan Check Approved 8/24/2021 ARSALAN SHABESTARI
Issued 8/26/2021 APPLICANT
Permit Finaled 5/16/2023 GABRIEL HERRERA

Permit Application Clearance Information

Tract Map conditions Cleared 1/31/2021 SARAHI ORTEGA
ZA Case Cleared 1/31/2021 SARAHI ORTEGA
ZI Cleared 1/31/2021 SARAHI ORTEGA

Contact Information

Contractor Gbc Construction; Lic. No.: 1004411-B 7170 MELODY DRIVE      FONTANA, CA 92336
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

EDMUND LUM, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
LUCIANO GAUNA, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
JAIME RIOS, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
ANDEY CHAPARRO, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
RYAN BARNES, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
PATRICK LIEBREGT, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
GLEN RAND, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
SHAWN ESHBACH, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
GABRIEL HERRERA, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/15/2021 Approved JEFFREY CORPUZ
BUILDING-Rough-Frame 11/10/2021 Partial Inspection JEFFREY CORPUZ
MERV13>=Rough 11/10/2021 Not Ready for Inspection JEFFREY CORPUZ
PLUMBING-Rough 4/15/2022 Approved GABRIEL HERRERA
HVAC-Rough 8/23/2022 Approved GABRIEL HERRERA
Insulation 8/23/2022 Approved GABRIEL HERRERA
Interior/Exterior Lathing 8/23/2022 Approved GABRIEL HERRERA
Drywall Nailing 9/7/2022 Approved GABRIEL HERRERA
ELECTRICAL-Rough 1/13/2023 Approved GABRIEL HERRERA
Service/Power Release 1/13/2023 Approved GABRIEL HERRERA
BUILDING-Rough-Frame 5/16/2023 Approved GABRIEL HERRERA
ELECTRICAL-Final 5/16/2023 Approved GABRIEL HERRERA
Final 5/16/2023 Permit Finaled GABRIEL HERRERA
HVAC-Final 5/16/2023 Approved GABRIEL HERRERA
MERV13>=Final 5/16/2023 Approved GABRIEL HERRERA
MERV13>=Rough 5/16/2023 Approved GABRIEL HERRERA
PLUMBING-Final 5/16/2023 Approved GABRIEL HERRERA
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Approved GABRIEL HERRERA
Smoke Detectors 5/16/2023 Approved GABRIEL HERRERA