8849 S CIMARRON ST 90047
Certificate Information: 8849 S CIMARRON ST 90047
- Application / Permit
- 20016-10000-24626
- Plan Check / Job No.
- B20LA17972
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CHANGE (E) GARAGE TO A (N) ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 12/29/2020
- Issuing Office
- Current Status
- CofO Issued on 11/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 10/6/2020 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 10/8/2020 | APPLICANT |
| Applicant returned to address corrections | 11/30/2020 | LUKE GONZALES |
| Plan Check Approved | 12/11/2020 | RICARDO RAMIREZ |
| Issued | 12/29/2020 | APPLICANT |
| CofO in Progress | 11/10/2021 | FREDDIE RIVERA |
| CofO Issued | 11/18/2021 | DEROLD HAUFF |
| Permit Finaled | 11/18/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2020 | THOMAS LANG |
| Sewer availability | Cleared | 10/21/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2020 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/28/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/18/2021 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 3/5/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/18/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/6/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 4/6/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/3/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 6/4/2021 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 6/10/2021 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/11/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 6/11/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 6/11/2021 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Rough | 6/11/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 6/11/2021 | Partial Approval | FREDDIE RIVERA |
| Insulation | 6/18/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 6/28/2021 | Approved | CALEB MEISTER |
| HVAC-Rough | 6/28/2021 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 7/8/2021 | Partial Approval | SABAS ALONSO |
| Final | 10/26/2021 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 10/26/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/26/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 10/26/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 11/2/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 11/2/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/2/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 11/2/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 11/9/2021 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 11/9/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/9/2021 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 11/9/2021 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 11/9/2021 | Approved | FREDDIE RIVERA |