8849 S CIMARRON ST 90047

Certificate Information: 8849 S CIMARRON ST 90047

Application / Permit
20016-10000-24626
Plan Check / Job No.
B20LA17972
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CHANGE (E) GARAGE TO A (N) ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 12/29/2020
Issuing Office
Current Status
CofO Issued on 11/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2020 APPLICANT
Assigned to Plan Check Engineer 10/5/2020 FARSHAD ALIMOHAMADI
Corrections Issued 10/6/2020 FARSHAD ALIMOHAMADI
Building Plans Picked Up 10/8/2020 APPLICANT
Applicant returned to address corrections 11/30/2020 LUKE GONZALES
Plan Check Approved 12/11/2020 RICARDO RAMIREZ
Issued 12/29/2020 APPLICANT
CofO in Progress 11/10/2021 FREDDIE RIVERA
CofO Issued 11/18/2021 DEROLD HAUFF
Permit Finaled 11/18/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/21/2020 THOMAS LANG
Sewer availability Cleared 10/21/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/22/2020 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/28/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 2/18/2021 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 3/5/2021 Approved FREDDIE RIVERA
Footing/Foundation/Slab 3/18/2021 Approved FREDDIE RIVERA
Footing/Foundation/Slab 4/6/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 4/6/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 5/3/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 6/4/2021 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 6/10/2021 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 6/11/2021 Approved FREDDIE RIVERA
Green Building Rough 6/11/2021 Approved FREDDIE RIVERA
HVAC-Rough 6/11/2021 Corrections Issued FREDDIE RIVERA
METHANE-Rough 6/11/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 6/11/2021 Partial Approval FREDDIE RIVERA
Insulation 6/18/2021 Approved FREDDIE RIVERA
Drywall Nailing 6/28/2021 Approved CALEB MEISTER
HVAC-Rough 6/28/2021 Approved CALEB MEISTER
Interior/Exterior Lathing 7/8/2021 Partial Approval SABAS ALONSO
Final 10/26/2021 Corrections Issued FREDDIE RIVERA
Green Building Final 10/26/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/26/2021 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 10/26/2021 Not Ready for Inspection FREDDIE RIVERA
Final 11/2/2021 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 11/2/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/2/2021 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 11/2/2021 Not Ready for Inspection FREDDIE RIVERA
Final 11/9/2021 Conditional Approval FREDDIE RIVERA
Green Building Final 11/9/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/9/2021 SGSOV Approved FREDDIE RIVERA
Service/Power Release 11/9/2021 Approved FREDDIE RIVERA
Smoke Detectors 11/9/2021 Approved FREDDIE RIVERA