8126 S REGIS WAY 90045
Certificate Information: 8126 S REGIS WAY 90045
- Application / Permit
- 20016-10000-24448
- Plan Check / Job No.
- B20LA17859
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADUs. Covert Existing recreation room(312 sq ft) above (E) garage into accessory dwelling unit per LAMC 12.22 A.33(b)(5)
- Permit Issued
- Issued on 2/12/2022
- Issuing Office
- Current Status
- Issued on 2/12/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2020 | MONICA RAMIREZ |
| Corrections Issued | 10/13/2020 | MONICA RAMIREZ |
| Quality Review Completed | 10/15/2020 | TU HUA |
| Applicant returned to address corrections | 12/28/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 2/8/2021 | MONICA RAMIREZ |
| Plan Check Approved | 12/21/2021 | MONICA RAMIREZ |
| Issued | 2/12/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2020 | DINAH GARIN |
| Sewer availability | Cleared | 12/4/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2020 | DINAH GARIN |
| Specific Plan | Cleared | 3/24/2021 | FREDDY GARCIA |
| Construction near power lines | Cleared | 12/21/2021 | TINA MIRANDA |
Contact Information
| Architect | Norris,, Tommy; Lic. No.: C37119 | 475 WASHINGTON BLVD MARINA DEL REY, CA 90292 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 3/18/2022 | No Access for Inspection | BOBBY KEY |
| HVAC-Rough | 7/14/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/14/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/23/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 8/23/2022 | Approved | BOBBY KEY |
| HVAC-Final | 8/23/2022 | Approved | BOBBY KEY |
| Underground Mechanical | 8/23/2022 | Approved | BOBBY KEY |
| Insulation | 9/13/2022 | Approved | BOBBY KEY |
| Sewer | 9/13/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 10/6/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/13/2022 | Approved | BOBBY KEY |