1624 1/2 W 55TH ST 90062
Certificate Information: 1624 1/2 W 55TH ST 90062
- Application / Permit
- 20016-10000-24408
- Plan Check / Job No.
- B20LA17810
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage to Accessory Dwelling unit per LAMC 12.22 A.33(c) and (d). All work per WFPP.
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- CofO Issued on 3/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2020 | CHRISTOPHER KOMANCHECK |
| Corrections Issued | 10/22/2020 | CHRISTOPHER KOMANCHECK |
| Building Plans Picked Up | 10/27/2020 | APPLICANT |
| Plan Check Approved | 4/23/2021 | SINA KHOSRAVI |
| Issued | 5/20/2021 | APPLICANT |
| CofO in Progress | 3/14/2022 | SABAS ALONSO |
| Permit Finaled | 3/16/2022 | DEROLD HAUFF |
| CofO Issued | 3/16/2022 | DEROLD HAUFF |
| Permit Finaled | 3/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2021 | JEANIE LAM |
| Sewer availability | Cleared | 1/7/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2021 | JEANIE LAM |
| Tenant Habitability Plan | Cleared | 3/24/2021 | PHILLIP MUNGUIA |
| Community Plan Implem. Overlay | Cleared | 4/5/2021 | RAFAEL FONTES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/7/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/7/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 6/7/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 6/7/2021 | Conditional Approval | FREDDIE RIVERA |
| Pre-Inspection | 6/7/2021 | Corrections Issued | FREDDIE RIVERA |
| Special/Order Compliance | 7/28/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/3/2021 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 9/9/2021 | No Access for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 9/13/2021 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 9/28/2021 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 9/28/2021 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 9/28/2021 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/4/2021 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 10/4/2021 | Approved | SABAS ALONSO |
| Green Building Rough | 10/4/2021 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 10/4/2021 | Approved | SABAS ALONSO |
| Insulation | 10/8/2021 | No Access for Inspection | JOAQUIN GREENOUGH |
| Insulation | 10/13/2021 | Approved | SABAS ALONSO |
| Drywall Nailing | 10/29/2021 | Not Ready for Inspection | SABAS ALONSO |
| Drywall Nailing | 11/2/2021 | Approved | SABAS ALONSO |
| Final | 12/14/2021 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/14/2021 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/14/2021 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 12/14/2021 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 12/20/2021 | No Access for Inspection | SABAS ALONSO |
| Service/Power Release | 12/20/2021 | No Access for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 2/1/2022 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 2/25/2022 | Not Ready for Inspection | HORACE FULTZ |
| Final | 3/2/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 3/2/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/2/2022 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 3/2/2022 | Approved | SABAS ALONSO |
| Final | 3/9/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 3/11/2022 | OK to Issue CofO | SABAS ALONSO |