1624 1/2 W 55TH ST 90062

Certificate Information: 1624 1/2 W 55TH ST 90062

Application / Permit
20016-10000-24408
Plan Check / Job No.
B20LA17810
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage to Accessory Dwelling unit per LAMC 12.22 A.33(c) and (d). All work per WFPP.
Permit Issued
Issued on 5/20/2021
Issuing Office
Current Status
CofO Issued on 3/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2020 APPLICANT
Assigned to Plan Check Engineer 10/21/2020 CHRISTOPHER KOMANCHECK
Corrections Issued 10/22/2020 CHRISTOPHER KOMANCHECK
Building Plans Picked Up 10/27/2020 APPLICANT
Plan Check Approved 4/23/2021 SINA KHOSRAVI
Issued 5/20/2021 APPLICANT
CofO in Progress 3/14/2022 SABAS ALONSO
Permit Finaled 3/16/2022 DEROLD HAUFF
CofO Issued 3/16/2022 DEROLD HAUFF
Permit Finaled 3/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/7/2021 JEANIE LAM
Sewer availability Cleared 1/7/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/8/2021 JEANIE LAM
Tenant Habitability Plan Cleared 3/24/2021 PHILLIP MUNGUIA
Community Plan Implem. Overlay Cleared 4/5/2021 RAFAEL FONTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/7/2021 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 6/7/2021 Approved FREDDIE RIVERA
Green Building Rough 6/7/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 6/7/2021 Conditional Approval FREDDIE RIVERA
Pre-Inspection 6/7/2021 Corrections Issued FREDDIE RIVERA
Special/Order Compliance 7/28/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 9/3/2021 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 9/9/2021 No Access for Inspection SABAS ALONSO
Footing/Foundation/Slab 9/13/2021 Approved SABAS ALONSO
ELECTRICAL-Rough 9/28/2021 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 9/28/2021 Approved SABAS ALONSO
PLUMBING-Rough 9/28/2021 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 10/4/2021 Approved SABAS ALONSO
ELECTRICAL-Rough 10/4/2021 Approved SABAS ALONSO
Green Building Rough 10/4/2021 Approved SABAS ALONSO
PLUMBING-Rough 10/4/2021 Approved SABAS ALONSO
Insulation 10/8/2021 No Access for Inspection JOAQUIN GREENOUGH
Insulation 10/13/2021 Approved SABAS ALONSO
Drywall Nailing 10/29/2021 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 11/2/2021 Approved SABAS ALONSO
Final 12/14/2021 Corrections Issued SABAS ALONSO
Green Building Final 12/14/2021 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/14/2021 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 12/14/2021 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 12/20/2021 No Access for Inspection SABAS ALONSO
Service/Power Release 12/20/2021 No Access for Inspection SABAS ALONSO
ELECTRICAL-Final 2/1/2022 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 2/25/2022 Not Ready for Inspection HORACE FULTZ
Final 3/2/2022 Not Ready for Inspection SABAS ALONSO
Green Building Final 3/2/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Approved SABAS ALONSO
Smoke Detectors 3/2/2022 Approved SABAS ALONSO
Final 3/9/2022 Not Ready for Inspection FREDDIE RIVERA
Final 3/11/2022 OK to Issue CofO SABAS ALONSO