20422 W CHASE ST 91306

Certificate Information: 20422 W CHASE ST 91306

Application / Permit
20016-10000-24264
Plan Check / Job No.
B20LA17724
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Convert (E) detached recreation room into ADU per LAMC 12.22 A.33(c)&(d) with addition. All work per Wood Frame Prescriptive Design.
Permit Issued
Issued on 3/28/2024
Issuing Office
Current Status
CofO Issued on 3/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 ZAW HAN
Corrections Issued 11/9/2020 ZAW HAN
Quality Review Completed 11/22/2020 TU HUA
Applicant returned to address corrections 7/12/2021 ZAW HAN
Applicant returned to address corrections 9/25/2023 ZAW HAN
Applicant returned to address corrections 9/26/2023 ZAW HAN
Plan Check Approved 3/8/2024 ZAW HAN
Issued 3/28/2024 APPLICANT
CofO in Progress 1/9/2025 JEFFREY HARTLINE
Permit Finaled 3/20/2025 JOHN JANSON
Permit Finaled 3/20/2025 JOHN JANSON
CofO Issued 3/20/2025 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 3/20/2021 RIDWAN HARDY
Construction within easement Cleared 3/20/2021 RIDWAN HARDY
Address approval Cleared 5/24/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/24/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/26/2021 CARLOS AGUILERA
Sewer availability Cleared 5/26/2021 CARLOS AGUILERA
Green Code Cleared 7/12/2021 ZAW HAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/24/2024 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Partial Approval JEFFREY HARTLINE
Green Building Rough 8/21/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 9/19/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 9/19/2024 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 9/19/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 9/26/2024 Approved CHRIS CHRISTENSEN
Green Building Rough 9/26/2024 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 9/26/2024 Approved CHRIS CHRISTENSEN
Wood Frame 9/26/2024 Approved CHRIS CHRISTENSEN
Insulation 10/3/2024 Corrections Issued CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/3/2024 Partial Approval CHRIS CHRISTENSEN
Insulation 10/11/2024 Approved JEFFREY HARTLINE
Drywall Nailing 10/21/2024 Approved JEFFREY HARTLINE
Green Building Rough 10/21/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 11/14/2024 Not Ready for Inspection JEFFREY HARTLINE
Final 12/30/2024 Corrections Issued JEFFREY HARTLINE
Green Building Final 12/30/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 12/30/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Final 1/8/2025 Approved JEFFREY HARTLINE
Final 1/8/2025 OK to Issue CofO JEFFREY HARTLINE
HVAC-Final 1/8/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 1/8/2025 Approved JEFFREY HARTLINE
Service/Power Release 1/10/2025 Approved JEFFREY HARTLINE