712 N SEWARD ST 90038

Certificate Information: 712 N SEWARD ST 90038

Application / Permit
20016-10000-24245
Plan Check / Job No.
B20LA17714
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Exterior and Interior renovation & addition of (E) 2-story type-VB office Building including facade renovation, enlarged toilet rooms, additional and renovated stairs& new roof deck .
Permit Issued
Issued on 4/13/2021
Issuing Office
Current Status
CofO Issued on 1/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2020 APPLICANT
Assigned to Plan Check Engineer 10/8/2020 GARO TELMI
Corrections Issued 10/14/2020 GARO TELMI
Quality Review Completed 10/15/2020 CHAD DOI
Building Plans Picked Up 10/16/2020 APPLICANT
Disabled Access Plans Picked Up 10/30/2020 APPLICANT
Applicant returned to address corrections 11/12/2020 GARO TELMI
Applicant returned to address corrections 11/24/2020 GARO TELMI
Applicant returned to address corrections 12/22/2020 GARO TELMI
Applicant returned to address corrections 2/4/2021 GARO TELMI
Green Plans Picked Up 2/24/2021 APPLICANT
Plan Check Approved 4/9/2021 GARO TELMI
Issued 4/13/2021 APPLICANT
CofO in Progress 1/28/2022 JONATHAN QUACH
CofO Issued 1/28/2022 ERNESTO CORRAL
Permit Finaled 1/28/2022 ERNESTO CORRAL

Permit Application Clearance Information

Prkng lot landscape/Water mgmt Cleared 10/30/2020 LOUIS ORTEGA
ZI Cleared 10/30/2020 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 11/4/2020 JEANIE LAM
Highway dedication Cleared 11/4/2020 JEANIE LAM
Low Impact Development Cleared 12/9/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/16/2020 JEANIE LAM
Work Adjacent to Public Way Cleared 12/18/2020 ARMEN SARKISIAN
DAS Clearance Cleared 2/4/2021 GARO TELMI
Green Code Cleared 2/23/2021 GARO TELMI

Contact Information

Architect House,, James Douglas; Lic. No.: C15526 10125 WASHINGTON BLVD      CULVER CITY, CA 90232
Contractor E P I Construction Inc; Lic. No.: 865616-B 12345 VENTURA BLVD SUITE H      STUDIO CITY, CA 91604

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/14/2021 Approved RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 5/7/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/7/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 5/10/2021 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 5/21/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 5/26/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/26/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 6/2/2021 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 6/2/2021 Partial Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 6/8/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/9/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 6/16/2021 Partial Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 7/1/2021 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 7/1/2021 Partial Approval JONATHAN QUACH
Green Building Rough 7/1/2021 Not Ready for Inspection JONATHAN QUACH
METHANE-Rough 7/1/2021 Not Ready for Inspection JONATHAN QUACH
Wood Frame 7/1/2021 Corrections Issued JONATHAN QUACH
Green Building Rough 7/7/2021 Not Ready for Inspection JONATHAN QUACH
METHANE-Rough 7/7/2021 Approved JONATHAN QUACH
Wood Frame 7/7/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 7/19/2021 Conditional Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 8/23/2021 Partial Approval JONATHAN QUACH
Green Building Rough 8/23/2021 Not Ready for Inspection JONATHAN QUACH
Wood Frame 8/23/2021 Partial Approval JONATHAN QUACH
Deputy Wood Construction 9/9/2021 Conditional Approval RUSSELL BONVOULOIR
Green Building Rough 9/10/2021 Partial Inspection RUSSELL BONVOULOIR
Wood Frame 9/10/2021 Partial Approval RUSSELL BONVOULOIR
Green Building Rough 9/17/2021 Approved TIMOTHY BUXTON
Insulation 9/17/2021 Partial Approval TIMOTHY BUXTON
Wood Frame 9/17/2021 Partial Approval TIMOTHY BUXTON
Insulation 10/28/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 11/1/2021 Partial Approval SORIN CIRSTOIU
Wood Frame 11/8/2021 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 11/16/2021 Partial Approval SORIN CIRSTOIU
Interior/Exterior Lathing 11/24/2021 Approved JONATHAN QUACH
Final 12/27/2021 Not Ready for Inspection SORIN CIRSTOIU
Green Building Final 12/27/2021 Not Ready for Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 12/27/2021 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 12/27/2021 Not Ready for Inspection SORIN CIRSTOIU
Wood Frame 12/27/2021 Not Ready for Inspection SORIN CIRSTOIU
Final 1/21/2022 Partial Inspection JONATHAN QUACH
Green Building Final 1/21/2022 Not Ready for Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 1/21/2022 SGSOV Approved JONATHAN QUACH
Smoke Detectors 1/21/2022 Not Ready for Inspection JONATHAN QUACH
Wood Frame 1/21/2022 Approved JONATHAN QUACH
Final 1/25/2022 Not Ready for Inspection JONATHAN QUACH
Green Building Final 1/25/2022 Approved JONATHAN QUACH
Smoke Detectors 1/25/2022 Approved JONATHAN QUACH
Final 1/27/2022 Conditional Approval JONATHAN QUACH