12926 W PIERCE ST 91331
Certificate Information: 12926 W PIERCE ST 91331
- Application / Permit
- 20016-10000-24100
- Plan Check / Job No.
- B20LA17609
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Packaging Business
- Work Description
- E-PLAN: Tenant improvement and change of use from warehouse to food packaging facility.
- Permit Issued
- Issued on 11/19/2020
- Issuing Office
- Current Status
- CofO Issued on 7/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2020 | LARRY LEE |
| Corrections Issued | 10/13/2020 | LARRY LEE |
| Quality Review Completed | 10/23/2020 | MINYE PAK |
| Applicant returned to address corrections | 10/27/2020 | LARRY LEE |
| Applicant returned to address corrections | 11/9/2020 | LARRY LEE |
| Applicant returned to address corrections | 11/12/2020 | LARRY LEE |
| Plan Check Approved | 11/12/2020 | LARRY LEE |
| Issued | 11/19/2020 | APPLICANT |
| CofO in Progress | 7/6/2021 | ANDREW DORSO |
| CofO Issued | 7/30/2021 | JEFFREY DURAN |
| Permit Finaled | 7/30/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/4/2020 | ADRIAN CASTRO |
| ZA Case | Cleared | 11/9/2020 | ANACANY HURTADO |
| ZA Case | Cleared | 11/9/2020 | ANACANY HURTADO |
| ZI | Cleared | 11/9/2020 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Total Construction; Lic. No.: 566676-B | 25263 DE WOLFE RD SANTA CLARITA, CA 91321 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 11/25/2020 | No Access for Inspection | DANIEL VARNUM |
| Structural Steel Frame | 11/25/2020 | No Access for Inspection | DANIEL VARNUM |
| Drywall Nailing | 11/30/2020 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 11/30/2020 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 12/23/2020 | Approved | ANDREW DORSO |
| T-Bar Ceiling | 12/23/2020 | Not Ready for Inspection | ANDREW DORSO |
| T-Bar Ceiling | 2/1/2021 | Approved | ANDREW DORSO |
| Final | 6/21/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| METHANE-Final | 6/21/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| SGSOV-Seismic Gas S/O Valve | 6/21/2021 | SGSOV Not Ready | HAMID PISHEHVAR |
| Smoke Detectors | 6/21/2021 | Not Ready for Inspection | HAMID PISHEHVAR |
| Final | 6/23/2021 | OK to Issue CofO | ANDREW DORSO |
| METHANE-Final | 6/23/2021 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 6/23/2021 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 6/23/2021 | Approved | ANDREW DORSO |