663 W 29TH ST 90731

Certificate Information: 663 W 29TH ST 90731

Application / Permit
20016-10000-23919
Plan Check / Job No.
B20LA17522
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: Install 2 Cantilever Columns
Permit Issued
Issued on 2/1/2021
Issuing Office
Current Status
CofC Issued on 4/21/2021

Permit Application Status History

Submitted 9/23/2020 APPLICANT
Assigned to Plan Check Engineer 10/14/2020 JESSE VIDUYA
Corrections Issued 10/21/2020 JESSE VIDUYA
Quality Review Completed 10/26/2020 HANS SANTIAGO
Applicant returned to address corrections 11/9/2020 JESSE VIDUYA
Plan Check Approved 11/18/2020 JESSE VIDUYA
Issued 2/1/2021 APPLICANT
OK for CofC 4/19/2021 JOEY BUCHANAN
CofC Issued 4/21/2021 NICK LAROCCA

Permit Application Clearance Information

Tenant Habitability Plan Cleared 2/1/2021 PHILLIP MUNGUIA

Contact Information

Contractor Retrofit 1; Lic. No.: 1003868-B 19326 VENTURA BLVD STE 200      TARZANA, CA 91356
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/18/2021 Approved JOEY BUCHANAN
Deputy Drilled-In Anchors 3/22/2021 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 3/22/2021 Approved JOEY BUCHANAN
Footing/Foundation/Slab 3/23/2021 Approved JOEY BUCHANAN
Structural Steel Frame 3/23/2021 Conditional Approval JOEY BUCHANAN
Wood Frame 3/23/2021 Approved JOEY BUCHANAN
Interior/Exterior Lathing 4/5/2021 Corrections Issued JOEY BUCHANAN
Final 4/19/2021 OK for CofC JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 4/19/2021 SGSOV No Gas JOEY BUCHANAN
Smoke Detectors 4/19/2021 Approved JOEY BUCHANAN