3115 W LACLEDE AVE 1-3 90039

Certificate Information: 3115 W LACLEDE AVE 1-3 90039

Application / Permit
20016-10000-23831
Plan Check / Job No.
B20LA17434
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EXISTING APARTMENT UNIT B 1ST FLOOR TO BE CONVERTED INTO ADU 534 ST AND CARPORT TO BE CONVERTED INTO BEDROOM FOR PROPOSED ATTACHED ADU PER LAMC 12.22 A33(c)&(e).
Permit Issued
Issued on 10/3/2021
Issuing Office
Current Status
CofO Issued on 12/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2020 APPLICANT
Assigned to Plan Check Engineer 10/7/2020 ZAW HAN
Corrections Issued 10/13/2020 ZAW HAN
Plan Check Approved 7/28/2021 ZAW HAN
Issued 10/3/2021 APPLICANT
Building Plans Picked Up 11/1/2021 APPLICANT
CofO in Progress 12/15/2022 MARK FERRARI
CofO Issued 12/15/2022 ERNESTO CORRAL
Permit Finaled 12/15/2022 ERNESTO CORRAL

Permit Application Clearance Information

Highway dedication Cleared 11/4/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 11/10/2020 JUAN ASHTON
"Q" conditions Cleared 1/6/2021 DENZEL HENDERSON
ZI Cleared 1/6/2021 DENZEL HENDERSON
Address approval Cleared 1/7/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 1/7/2021 CECILIO NAVARRO
Sewer availability Cleared 2/3/2021 CECILIO NAVARRO
Tenant Habitability Plan Cleared 6/21/2021 ISMAEL HERNANDEZ

Contact Information

Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/4/2021 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 1/14/2022 Partial Inspection MARK FERRARI
Insulation 1/14/2022 Partial Inspection MARK FERRARI
Green Building Rough 2/24/2022 Approved MARK FERRARI
Wood Frame 2/24/2022 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 4/14/2022 Not Ready for Inspection BRUCE CAMPBELL
Deputy Drilled-In Anchors 4/21/2022 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 4/22/2022 Not Ready for Inspection BRUCE CAMPBELL
Wood Frame 5/13/2022 Not Ready for Inspection MARK FERRARI
Deputy Wood Construction 5/26/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/10/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/17/2022 Approved MARK FERRARI
Insulation 7/25/2022 Approved MARK FERRARI
Drywall Nailing 8/1/2022 Approved MARK FERRARI
Final 8/22/2022 Conditional Approval MARK FERRARI
Green Building Final 8/22/2022 Approved MARK FERRARI
Smoke Detectors 8/22/2022 Approved MARK FERRARI
Wood Frame 8/22/2022 Approved MARK FERRARI