3115 W LACLEDE AVE 1-3 90039
Certificate Information: 3115 W LACLEDE AVE 1-3 90039
- Application / Permit
- 20016-10000-23831
- Plan Check / Job No.
- B20LA17434
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EXISTING APARTMENT UNIT B 1ST FLOOR TO BE CONVERTED INTO ADU 534 ST AND CARPORT TO BE CONVERTED INTO BEDROOM FOR PROPOSED ATTACHED ADU PER LAMC 12.22 A33(c)&(e).
- Permit Issued
- Issued on 10/3/2021
- Issuing Office
- Current Status
- CofO Issued on 12/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2020 | ZAW HAN |
| Corrections Issued | 10/13/2020 | ZAW HAN |
| Plan Check Approved | 7/28/2021 | ZAW HAN |
| Issued | 10/3/2021 | APPLICANT |
| Building Plans Picked Up | 11/1/2021 | APPLICANT |
| CofO in Progress | 12/15/2022 | MARK FERRARI |
| CofO Issued | 12/15/2022 | ERNESTO CORRAL |
| Permit Finaled | 12/15/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Highway dedication | Cleared | 11/4/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2020 | JUAN ASHTON |
| "Q" conditions | Cleared | 1/6/2021 | DENZEL HENDERSON |
| ZI | Cleared | 1/6/2021 | DENZEL HENDERSON |
| Address approval | Cleared | 1/7/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 1/7/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 2/3/2021 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 6/21/2021 | ISMAEL HERNANDEZ |
Contact Information
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/4/2021 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 1/14/2022 | Partial Inspection | MARK FERRARI |
| Insulation | 1/14/2022 | Partial Inspection | MARK FERRARI |
| Green Building Rough | 2/24/2022 | Approved | MARK FERRARI |
| Wood Frame | 2/24/2022 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 4/14/2022 | Not Ready for Inspection | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 4/21/2022 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 4/22/2022 | Not Ready for Inspection | BRUCE CAMPBELL |
| Wood Frame | 5/13/2022 | Not Ready for Inspection | MARK FERRARI |
| Deputy Wood Construction | 5/26/2022 | Conditional Approval | ERNESTO CORRAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 6/10/2022 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 6/17/2022 | Approved | MARK FERRARI |
| Insulation | 7/25/2022 | Approved | MARK FERRARI |
| Drywall Nailing | 8/1/2022 | Approved | MARK FERRARI |
| Final | 8/22/2022 | Conditional Approval | MARK FERRARI |
| Green Building Final | 8/22/2022 | Approved | MARK FERRARI |
| Smoke Detectors | 8/22/2022 | Approved | MARK FERRARI |
| Wood Frame | 8/22/2022 | Approved | MARK FERRARI |