3649 S HILLCREST DR 90016
Certificate Information: 3649 S HILLCREST DR 90016
- Application / Permit
- 20016-10000-23829
- Plan Check / Job No.
- B20LA17430
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTED EXISTING DETACHED GARAGE INTO AN ADU PER LAMC 12.22 A.33 (c) and (d)
- Permit Issued
- Issued on 10/30/2023
- Issuing Office
- Current Status
- CofO Issued on 9/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2020 | LUKE GONZALES |
| Corrections Issued | 9/30/2020 | LUKE GONZALES |
| Building Plans Picked Up | 10/13/2020 | APPLICANT |
| Plan Check Approved | 6/8/2021 | SHANGQIN XIE |
| Issued | 10/30/2023 | APPLICANT |
| CofO in Progress | 9/12/2025 | LUIS CASTRO |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
| CofO Issued | 9/13/2025 | DEROLD HAUFF |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/6/2021 | RIDWAN HARDY |
| Address approval | Cleared | 2/17/2021 | ROSA SILVA |
| Sewer availability | Cleared | 2/17/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2021 | ROSA SILVA |
Contact Information
| Contractor | G&S Building Inc; Lic. No.: 1070934-B | 10866 WASHINGTON BLVD 843 CULVER CITY, CA 90232 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/26/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 3/26/2024 | Corrections Issued | ANTHONY EGSON |
| Sewer | 3/26/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/2/2024 | Partial Inspection | ANTHONY EGSON |
| Sewer | 4/2/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/9/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/11/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/8/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 5/8/2024 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 5/8/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Underground Mechanical | 5/8/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/18/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/18/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 6/18/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 6/18/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/25/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 6/25/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 6/25/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/28/2024 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/4/2024 | Approved | ANTHONY EGSON |
| Insulation | 9/9/2024 | Corrections Issued | AMIR NAZARIAN |
| Insulation | 9/16/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/2/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/2/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 10/10/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 10/25/2024 | Approved | ALEX COLIN |
| Shower Pan | 10/25/2024 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 6/27/2025 | Approved | LUIS CASTRO |
| Final | 6/27/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 6/27/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 6/27/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 6/27/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 6/27/2025 | Approved | LUIS CASTRO |
| Final | 9/11/2025 | OK to Issue CofO | LUIS CASTRO |