14208 W REMINGTON ST 91331
Certificate Information: 14208 W REMINGTON ST 91331
- Application / Permit
- 20016-10000-23755
- Plan Check / Job No.
- B20LA17391
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE INTO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- Current Status
- CofO Issued on 10/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/3/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/18/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 4/6/2021 | RICARDO RAMIREZ |
| Issued | 4/12/2021 | APPLICANT |
| Building Plans Picked Up | 4/16/2021 | APPLICANT |
| CofO in Progress | 9/6/2023 | MICHEL ABAJAN |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
| CofO Issued | 10/13/2023 | RUBEN SALAS |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/26/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/27/2021 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/27/2021 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/29/2021 | No Access for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/10/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/10/2021 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 11/10/2021 | Approved | MICHEL ABAJAN |
| Insulation | 11/17/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 11/17/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2021 | Partial Approval | MICHEL ABAJAN |
| Drywall Nailing | 12/8/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/25/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/22/2022 | Approved | MICHEL ABAJAN |
| Final | 11/22/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 11/22/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 11/22/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/22/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 11/22/2022 | Approved | MICHEL ABAJAN |
| Final | 9/6/2023 | OK to Issue CofO | MICHEL ABAJAN |