2650 S TILDEN AVE 90064
Certificate Information: 2650 S TILDEN AVE 90064
- Application / Permit
- 20016-10000-23749
- Plan Check / Job No.
- B20LA17376
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. Convert Existing (20'x18') Detached Garage into ADU unit with small addition at the rear. per LAMC 12.22A.33 (b)(5)
- Permit Issued
- Issued on 4/28/2021
- Issuing Office
- Current Status
- CofO Issued on 5/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | CARLOS MONTES |
| Corrections Issued | 10/28/2020 | CARLOS MONTES |
| Quality Review Completed | 11/23/2020 | WING SUEN |
| Applicant returned to address corrections | 2/11/2021 | LAMAR DAVIS |
| Plan Check Approved | 4/7/2021 | MONICA RAMIREZ |
| Issued | 4/28/2021 | APPLICANT |
| CofO in Progress | 3/31/2022 | JOHNNY MIRANDA |
| No Progress | 4/8/2022 | KENNETH NAGLE |
| CofO in Progress | 4/29/2022 | KENNETH NAGLE |
| Permit Finaled | 5/3/2022 | DANIEL ORRANTE |
| CofO Issued | 5/3/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/3/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/14/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 12/14/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2020 | DINAH GARIN |
| Sewer availability | Cleared | 12/18/2020 | DINAH GARIN |
| Specific Plan | Cleared | 1/29/2021 | PEDRO AYALA |
| Grading Pre-Inspection | Cleared | 2/12/2021 | KIRK LINKLATER |
| Construction within easement | Cleared | 3/8/2021 | RIDWAN HARDY |
Contact Information
| Contractor | A G & B Construction Inc; Lic. No.: 891681-B | 1819 BELCROFT AVE SOUTH EL MONTE, CA 91733 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/1/2021 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 6/17/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Special/Order Compliance | 6/24/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2021 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/28/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/28/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 7/28/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/3/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/3/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/5/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 8/9/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/12/2021 | Not Ready for Inspection | KENNETH NAGLE |
| MERV13>=Rough | 8/12/2021 | Approved | KENNETH NAGLE |
| PLUMBING-Rough | 8/12/2021 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 8/25/2021 | Partial Approval | EVAN COOPER |
| Green Building Rough | 8/25/2021 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 9/1/2021 | Approved | EVAN COOPER |
| Green Building Rough | 9/1/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/1/2021 | Partial Approval | EVAN COOPER |
| Insulation | 9/14/2021 | Approved | MORRIS JACKSON |
| Drywall Nailing | 9/16/2021 | Approved | EVAN COOPER |
| Shower Pan | 10/4/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/6/2021 | Not Ready for Inspection | KRISTEN CAUSEY |
| Sewer | 11/16/2021 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 11/23/2021 | Approved | JOHNNY MIRANDA |
| Final | 12/15/2021 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 12/15/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 12/15/2021 | Not Ready for Inspection | EVAN COOPER |
| MERV13>=Final | 12/15/2021 | Not Ready for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/15/2021 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 12/15/2021 | Not Ready for Inspection | EVAN COOPER |
| Final | 2/18/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Service/Power Release | 3/9/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 3/24/2022 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/24/2022 | Approved | JOHNNY MIRANDA |
| Green Building Final | 3/24/2022 | Approved | JOHNNY MIRANDA |
| MERV13>=Final | 3/24/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 3/24/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 3/24/2022 | Approved | JOHNNY MIRANDA |
| Final | 3/30/2022 | OK to Issue CofO | JOHNNY MIRANDA |