4403 N MAMMOTH AVE 91423
Certificate Information: 4403 N MAMMOTH AVE 91423
- Application / Permit
- 20016-10000-23700
- Plan Check / Job No.
- B20LA17349
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: (1) SPECIAL CANTILEVERED COLUMN WITH GRADE BEAM.
- Permit Issued
- Issued on 10/13/2021
- Issuing Office
- Current Status
- CofC Issued on 8/4/2022
Permit Application Status History
| Submitted | 9/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2020 | DANIEL SANJUAN |
| Corrections Issued | 10/21/2020 | DANIEL SANJUAN |
| Quality Review Completed | 10/26/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 12/10/2020 | DANIEL SANJUAN |
| Applicant returned to address corrections | 12/24/2020 | DANIEL SANJUAN |
| Plan Check Approved | 1/19/2021 | DANIEL SANJUAN |
| Issued | 10/13/2021 | APPLICANT |
| OK for CofC | 4/20/2022 | KENNETH ROBERTS |
| CofC Issued | 8/4/2022 | KENNETH ROBERTS |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/27/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Zebra Construction Inc; Lic. No.: 1055609-B | 145 S FAIRFAX STE 200/300 LOS ANGELES, CA 90036 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/28/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Other (see comments) | 11/12/2021 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 11/16/2021 | Approved | KENNETH ROBERTS |
| Final | 11/16/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| Footing/Foundation/Slab | 11/16/2021 | Approved | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 11/16/2021 | SGSOV Not Ready | KENNETH ROBERTS |
| Smoke Detectors | 11/16/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| Structural Steel Frame | 11/16/2021 | Partial Approval | KENNETH ROBERTS |
| Wood Frame | 11/16/2021 | Partial Approval | KENNETH ROBERTS |
| Insulation | 11/19/2021 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 12/1/2021 | Approved | KENNETH ROBERTS |
| Final | 12/17/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 12/17/2021 | SGSOV Not Ready | KENNETH ROBERTS |
| Smoke Detectors | 12/17/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 1/5/2022 | SGSOV Not Ready | BRUCE CAMPBELL |
| Final | 1/14/2022 | No Access for Inspection | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 1/14/2022 | SGSOV Gas Company | KENNETH ROBERTS |
| Smoke Detectors | 1/14/2022 | No Access for Inspection | KENNETH ROBERTS |
| Final | 3/1/2022 | Corrections Issued | KENNETH ROBERTS |
| Smoke Detectors | 3/1/2022 | Approved | KENNETH ROBERTS |
| Final | 4/20/2022 | OK for CofC | KENNETH ROBERTS |