1304 W 41ST ST 90037
Certificate Information: 1304 W 41ST ST 90037
- Application / Permit
- 20016-10000-23651
- Plan Check / Job No.
- B20LA17311
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERSION & GROUND FLOOR ADDITION AT FRONT OF (E) GARAGE FOR (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/12/2021
- Issuing Office
- Current Status
- CofO Issued on 12/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | LAMAR DAVIS |
| Corrections Issued | 11/4/2020 | LAMAR DAVIS |
| Quality Review Completed | 11/5/2020 | TU HUA |
| Applicant returned to address corrections | 2/24/2021 | LAMAR DAVIS |
| Plan Check Approved | 3/9/2021 | LAMAR DAVIS |
| Issued | 3/12/2021 | APPLICANT |
| CofO in Progress | 11/28/2022 | SABAS ALONSO |
| Permit Finaled | 12/1/2022 | DEROLD HAUFF |
| CofO Issued | 12/1/2022 | DEROLD HAUFF |
| Permit Finaled | 12/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 11/25/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 1/11/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moayedi,, Kamran; Lic. No.: C35137 | 26180 ENTERPRISE WY STE 300 LAKE FOREST, CA 92630 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/11/2022 | Approved | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 2/23/2022 | Corrections Issued | HORACE FULTZ |
| Footing/Foundation/Slab | 2/23/2022 | Not Ready for Inspection | HORACE FULTZ |
| Excavation/Setback/Form/Re-Bar | 3/8/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 3/8/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/8/2022 | Approved | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 4/21/2022 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/5/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 5/5/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 5/5/2022 | Approved | SABAS ALONSO |
| Insulation | 5/16/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/24/2022 | Approved | SABAS ALONSO |
| Special/Order Compliance | 6/2/2022 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/7/2022 | Partial Approval | SABAS ALONSO |
| Shower Pan | 6/7/2022 | Approved | SABAS ALONSO |
| Insulation | 7/29/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 7/29/2022 | Approved | SABAS ALONSO |
| Final | 9/8/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 9/8/2022 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/8/2022 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 9/8/2022 | Approved | SABAS ALONSO |
| Final | 10/28/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 10/28/2022 | Approved | SABAS ALONSO |
| Final | 11/28/2022 | OK to Issue CofO | SABAS ALONSO |