1304 W 41ST ST 90037

Certificate Information: 1304 W 41ST ST 90037

Application / Permit
20016-10000-23651
Plan Check / Job No.
B20LA17311
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* CONVERSION & GROUND FLOOR ADDITION AT FRONT OF (E) GARAGE FOR (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/12/2021
Issuing Office
Current Status
CofO Issued on 12/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 LAMAR DAVIS
Corrections Issued 11/4/2020 LAMAR DAVIS
Quality Review Completed 11/5/2020 TU HUA
Applicant returned to address corrections 2/24/2021 LAMAR DAVIS
Plan Check Approved 3/9/2021 LAMAR DAVIS
Issued 3/12/2021 APPLICANT
CofO in Progress 11/28/2022 SABAS ALONSO
Permit Finaled 12/1/2022 DEROLD HAUFF
CofO Issued 12/1/2022 DEROLD HAUFF
Permit Finaled 12/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/25/2020 RENZ SORIANO
Sewer availability Cleared 11/25/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 12/8/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 1/11/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Moayedi,, Kamran; Lic. No.: C35137 26180 ENTERPRISE WY STE 300      LAKE FOREST, CA 92630

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/11/2022 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 2/23/2022 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 2/23/2022 Not Ready for Inspection HORACE FULTZ
Excavation/Setback/Form/Re-Bar 3/8/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 3/8/2022 Approved SABAS ALONSO
Underground Mechanical 3/8/2022 Approved SABAS ALONSO
Rough-Elec/Plmb/HVAC 4/21/2022 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 5/5/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 5/5/2022 Approved SABAS ALONSO
Green Building Rough 5/5/2022 Approved SABAS ALONSO
Insulation 5/16/2022 Approved SABAS ALONSO
Drywall Nailing 5/24/2022 Approved SABAS ALONSO
Special/Order Compliance 6/2/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 6/7/2022 Partial Approval SABAS ALONSO
Shower Pan 6/7/2022 Approved SABAS ALONSO
Insulation 7/29/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 7/29/2022 Approved SABAS ALONSO
Final 9/8/2022 Corrections Issued SABAS ALONSO
Green Building Final 9/8/2022 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/8/2022 SGSOV Approved SABAS ALONSO
Smoke Detectors 9/8/2022 Approved SABAS ALONSO
Final 10/28/2022 Not Ready for Inspection SABAS ALONSO
Green Building Final 10/28/2022 Approved SABAS ALONSO
Final 11/28/2022 OK to Issue CofO SABAS ALONSO