2426 S HALM AVE 90034

Certificate Information: 2426 S HALM AVE 90034

Application / Permit
20016-10000-23491
Plan Check / Job No.
B20LA17181
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing garage and ground floor addition to an ADU. HYDRANTS AND ACCESS JOINT STAMPING PILOT
Permit Issued
Issued on 3/19/2021
Issuing Office
Current Status
CofO Issued on 11/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2020 APPLICANT
Assigned to Plan Check Engineer 10/2/2020 JOE VO
Corrections Issued 10/2/2020 JOE VO
Quality Review Completed 10/20/2020 MINYE PAK
Applicant returned to address corrections 12/29/2020 JOE VO
Applicant returned to address corrections 2/16/2021 JOE VO
Plan Check Approved 2/19/2021 JOE VO
Issued 3/19/2021 APPLICANT
CofO in Progress 10/26/2021 EVAN COOPER
Permit Finaled 11/3/2021 KENNETH NAGLE
CofO Issued 11/3/2021 KENNETH NAGLE
Permit Finaled 11/3/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 11/13/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 11/16/2020 RENZ SORIANO
Sewer availability Cleared 11/30/2020 DINAH GARIN
Construction near power lines Cleared 2/9/2021 WALTER RAMIREZ
Hydrant and Access approval Cleared 2/10/2021 KURT CORRAL
Low Impact Development Cleared 2/18/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/24/2021 ROSA SILVA

Contact Information

Contractor Arrow Construction & Remodeling Inc; Lic. No.: 718685-B 1749 SOUTH SHERBOURNE DRIVE      LOS ANGELES, CA 90035
Engineer Shoraka,, Khojasteh Farhang; Lic. No.: C33555 1423 S BEVERLY GLEN UNIT A      LOS ANGELES, CA 90024

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/20/2021 Approved EVAN COOPER
Footing/Foundation/Slab 5/11/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 5/17/2021 Partial Approval EVAN COOPER
Footing/Foundation/Slab 5/28/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 7/2/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 7/2/2021 Not Ready for Inspection EVAN COOPER
Green Building Rough 7/2/2021 Not Ready for Inspection EVAN COOPER
MERV13>=Rough 7/2/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 7/2/2021 Approved EVAN COOPER
ELECTRICAL-Rough 7/21/2021 Approved KEVIN SARGSYAN
HVAC-Rough 7/21/2021 Approved KEVIN SARGSYAN
Sewer 7/26/2021 Approved KEVIN SARGSYAN
Underground Mechanical 7/26/2021 Corrections Issued KEVIN SARGSYAN
Underground Mechanical 7/28/2021 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 8/6/2021 Approved SHAVONNE ESPINOZA
Pre-Inspection 8/6/2021 Partial Inspection MORRIS JACKSON
Insulation 8/12/2021 Approved EVAN COOPER
Drywall Nailing 8/19/2021 Conditional Approval SHAVONNE ESPINOZA
BUILDING-Rough-Frame 8/26/2021 Approved EVAN COOPER
Drywall Nailing 8/26/2021 Approved EVAN COOPER
Green Building Rough 8/26/2021 Approved EVAN COOPER
Insulation 8/26/2021 Approved EVAN COOPER
Interior/Exterior Lathing 8/26/2021 Approved EVAN COOPER
MERV13>=Rough 8/26/2021 Approved EVAN COOPER
Shower Pan 8/26/2021 Approved EVAN COOPER
ELECTRICAL-Final 10/26/2021 Approved EVAN COOPER
Final 10/26/2021 OK to Issue CofO EVAN COOPER
Green Building Final 10/26/2021 Approved EVAN COOPER
HVAC-Final 10/26/2021 Approved EVAN COOPER
MERV13>=Final 10/26/2021 Approved EVAN COOPER
PLUMBING-Final 10/26/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/26/2021 SGSOV Approved EVAN COOPER
Service/Power Release 10/26/2021 Approved EVAN COOPER
Smoke Detectors 10/26/2021 Approved EVAN COOPER