10746 W WESCOTT AVE 91040
Certificate Information: 10746 W WESCOTT AVE 91040
- Application / Permit
- 20016-10000-23477
- Plan Check / Job No.
- B20LA17165
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - Convert existing 18 ft. x 18 ft. garage and expand existing garage by an additional 430 sf for a total area of 793 sf.
- Permit Issued
- Issued on 6/16/2021
- Issuing Office
- Current Status
- CofO Issued on 8/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 10/29/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/21/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 5/1/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 5/13/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 5/21/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 5/25/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 6/4/2021 | ARSALAN SHABESTARI |
| Issued | 6/16/2021 | APPLICANT |
| CofO in Progress | 3/21/2022 | MATTHEW NELSON |
| Permit Finaled | 8/17/2022 | DANIEL ORRANTE |
| CofO Issued | 8/17/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/17/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/8/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 4/19/2021 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 5/3/2021 | ARSALAN SHABESTARI |
| Low Impact Development | Cleared | 5/13/2021 | MARTIN FRAGOSO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/14/2021 | Conditional Approval | DANIEL ORRANTE |
| PLUMBING-Rough | 7/19/2021 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 7/23/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 10/14/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/28/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/28/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 10/28/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/28/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 10/28/2021 | Approved | MATTHEW NELSON |
| Insulation | 11/9/2021 | Conditional Approval | WILLIAM WREN |
| Interior/Exterior Lathing | 11/17/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 11/24/2021 | Approved | MATTHEW NELSON |
| Sewer | 12/23/2021 | Approved | MATTHEW NELSON |
| Final | 3/2/2022 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/2/2022 | Approved | MATTHEW NELSON |
| Green Building Final | 3/2/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/2/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 3/2/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 3/18/2022 | Approved | MATTHEW NELSON |
| Final | 3/18/2022 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 3/18/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 3/18/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 6/7/2022 | Approved | MATTHEW NELSON |