10746 W WESCOTT AVE 91040

Certificate Information: 10746 W WESCOTT AVE 91040

Application / Permit
20016-10000-23477
Plan Check / Job No.
B20LA17165
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan - Convert existing 18 ft. x 18 ft. garage and expand existing garage by an additional 430 sf for a total area of 793 sf.
Permit Issued
Issued on 6/16/2021
Issuing Office
Current Status
CofO Issued on 8/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 ARSALAN SHABESTARI
Corrections Issued 10/29/2020 ARSALAN SHABESTARI
Quality Review Completed 11/21/2020 PRANITA SHAH
Applicant returned to address corrections 5/1/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 5/13/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 5/21/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 5/25/2021 ARSALAN SHABESTARI
Plan Check Approved 6/4/2021 ARSALAN SHABESTARI
Issued 6/16/2021 APPLICANT
CofO in Progress 3/21/2022 MATTHEW NELSON
Permit Finaled 8/17/2022 DANIEL ORRANTE
CofO Issued 8/17/2022 DANIEL ORRANTE
Permit Finaled 8/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/8/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/8/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/8/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 4/19/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 5/3/2021 ARSALAN SHABESTARI
Low Impact Development Cleared 5/13/2021 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/14/2021 Conditional Approval DANIEL ORRANTE
PLUMBING-Rough 7/19/2021 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 7/23/2021 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Approved MATTHEW NELSON
PLUMBING-Rough 10/14/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/28/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 10/28/2021 Corrections Issued MATTHEW NELSON
Green Building Rough 10/28/2021 Approved MATTHEW NELSON
HVAC-Rough 10/28/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/28/2021 Approved MATTHEW NELSON
Insulation 11/9/2021 Conditional Approval WILLIAM WREN
Interior/Exterior Lathing 11/17/2021 Approved MATTHEW NELSON
Drywall Nailing 11/24/2021 Approved MATTHEW NELSON
Sewer 12/23/2021 Approved MATTHEW NELSON
Final 3/2/2022 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 3/2/2022 Approved MATTHEW NELSON
Green Building Final 3/2/2022 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Approved MATTHEW NELSON
Smoke Detectors 3/2/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 3/18/2022 Approved MATTHEW NELSON
Final 3/18/2022 OK to Issue CofO MATTHEW NELSON
HVAC-Final 3/18/2022 Approved MATTHEW NELSON
PLUMBING-Final 3/18/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 6/7/2022 Approved MATTHEW NELSON