1510 W 93RD ST 90047
Certificate Information: 1510 W 93RD ST 90047
- Application / Permit
- 20016-10000-23472
- Plan Check / Job No.
- B20LA17162
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERT GARAGE INTO ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/28/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2020 | SHANGQIN XIE |
| Corrections Issued | 9/25/2020 | SHANGQIN XIE |
| Applicant returned to address corrections | 3/26/2021 | LUKE GONZALES |
| Plan Check Approved | 4/15/2021 | LUKE GONZALES |
| Building Plans Picked Up | 4/16/2021 | APPLICANT |
| Issued | 4/28/2021 | APPLICANT |
| Permit Finaled | 4/30/2025 | DEROLD HAUFF |
| CofO Issued | 4/30/2025 | DEROLD HAUFF |
| Permit Finaled | 4/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/22/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 10/22/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 12/1/2020 | MATTHEW CRAIG |
| Construction within easement | Cleared | 3/10/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/26/2021 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 11/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/7/2022 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/16/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 11/1/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 11/6/2024 | Partial Approval | LUIS CASTRO |
| Footing/Foundation/Slab | 11/14/2024 | Partial Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 12/2/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 12/2/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 12/2/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Rough | 12/2/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 12/2/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 12/4/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 12/4/2024 | Conditional Approval | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 12/9/2024 | Corrections Issued | JOSE MACIAS |
| Drywall Nailing | 12/16/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 12/16/2024 | Corrections Issued | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/18/2024 | Corrections Issued | BARRY HACHE |
| Interior/Exterior Lathing | 12/18/2024 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 12/31/2024 | Conditional Approval | AMIR NAZARIAN |
| Drywall Nailing | 12/31/2024 | Conditional Approval | AMIR NAZARIAN |
| Green Building Rough | 12/31/2024 | Approved | AMIR NAZARIAN |
| Insulation | 12/31/2024 | Conditional Approval | AMIR NAZARIAN |
| Interior/Exterior Lathing | 12/31/2024 | Corrections Issued | AMIR NAZARIAN |
| Interior/Exterior Lathing | 1/3/2025 | Partial Approval | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 2/11/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 2/11/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 2/11/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 2/11/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 2/11/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Final | 2/11/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 2/11/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 2/11/2025 | Corrections Issued | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/11/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 2/11/2025 | Approved | NICHOLAS LOPEZ |
| Final | 2/18/2025 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 2/18/2025 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 2/18/2025 | SGSOV Approved | MICHAEL LEWIS |
| Final | 4/25/2025 | Conditional Approval | JOSE MACIAS |
| Green Building Final | 4/25/2025 | Approved | JOSE MACIAS |
| Service/Power Release | 4/25/2025 | Approved | JOSE MACIAS |