1150 S OLIVE ST SUITE 800 90015
Certificate Information: 1150 S OLIVE ST SUITE 800 90015
- Application / Permit
- 20016-10000-23468
- Plan Check / Job No.
- B20LA17157
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR IMPROVEMENT SCOPE TO INCLUDE DEMOLITION AND CONSTRUCTION OF NEW NONLOAD-BEARING PARTITIONS, CEILINGS, DOORS, AND FINISHES. NEW UNISEX SINGLE-ACCOMMODATION RESTROOM.
- Permit Issued
- Issued on 3/26/2021
- Issuing Office
- Current Status
- Permit Finaled on 9/15/2021
Permit Application Status History
| Submitted | 9/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 10/1/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/11/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 2/10/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 3/24/2021 | GEORGE ALVAREZ |
| Issued | 3/26/2021 | APPLICANT |
| Building Plans Picked Up | 4/9/2021 | APPLICANT |
| Permit Finaled | 9/14/2021 | TIMOTHY BUXTON |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 1/4/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 1/12/2021 | DAVID URITA |
Contact Information
| Architect | Guieb,, Melvin B; Lic. No.: C36943 | 30106 N CAMBRIDGE AVENUE CASTAIC, CA 91384 |
| Contractor | Phoenix Construction And Management Inc; Lic. No.: 815136-B | 515 S FLOWER STREET, STE 1270 LOS ANGELES, CA 90071 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 5/27/2021 | Conditional Approval | DANIEL COLLINS |
| Drywall Nailing | 6/10/2021 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 6/10/2021 | Partial Approval | KATY RAMIREZ |
| T-Bar Ceiling | 7/15/2021 | Approved | DANIEL COLLINS |
| Final | 8/27/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 8/27/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 8/27/2021 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 8/27/2021 | Approved | TIMOTHY BUXTON |
| Final | 9/8/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 9/8/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 9/14/2021 | Permit Finaled | TIMOTHY BUXTON |
| Green Building Final | 9/14/2021 | Approved | TIMOTHY BUXTON |