3889 S WELLAND AVE 90008
Certificate Information: 3889 S WELLAND AVE 90008
- Application / Permit
- 20016-10000-23253
- Plan Check / Job No.
- B20LA17025
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) DETACHED GARAGE TO ADU.
- Permit Issued
- Issued on 11/19/2020
- Issuing Office
- Current Status
- CofO Issued on 6/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2020 | AMIR DANAI |
| Corrections Issued | 9/22/2020 | AMIR DANAI |
| Applicant returned to address corrections | 10/15/2020 | JESSE JIMENEZ |
| Plan Check Approved | 11/17/2020 | SAMUEL GONZALEZ |
| Issued | 11/19/2020 | APPLICANT |
| Building Plans Picked Up | 2/24/2021 | APPLICANT |
| CofO in Progress | 5/29/2021 | DAVID FEILER |
| Permit Finaled | 6/9/2021 | DEROLD HAUFF |
| CofO Issued | 6/9/2021 | DEROLD HAUFF |
| Permit Finaled | 6/9/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 10/7/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 10/7/2020 | JUAN ASHTON |
| Construction near power lines | Cleared | 10/28/2020 | OSCAR CASTRO |
Contact Information
| Contractor | Valencia Construction Company; Lic. No.: 1015167-B | 12069 SMALLWOOD AVE DOWNEY, CA 90242 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/7/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 1/7/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 1/7/2021 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/25/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 2/25/2021 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 2/25/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 2/25/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 2/25/2021 | Not Ready for Inspection | DAVID FEILER |
| Deputy Drilled-In Anchors | 3/5/2021 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 4/21/2021 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 4/21/2021 | Approved | DAVID FEILER |
| Green Building Rough | 4/21/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 4/21/2021 | Approved | DAVID FEILER |
| Underground Mechanical | 4/21/2021 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 4/30/2021 | Approved | ROBERT MCDOWELL |
| Sewer | 4/30/2021 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 4/30/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 5/3/2021 | Not Ready for Inspection | SABAS ALONSO |
| Drywall Nailing | 5/11/2021 | Approved | SABAS ALONSO |
| Insulation | 5/11/2021 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 5/11/2021 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/21/2021 | Approved | DAVID FEILER |
| Final | 5/21/2021 | Corrections Issued | DAVID FEILER |
| Green Building Final | 5/21/2021 | Approved | DAVID FEILER |
| Green Building Rough | 5/21/2021 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 5/21/2021 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 5/21/2021 | Approved | DAVID FEILER |
| Final | 5/28/2021 | OK to Issue CofO | DAVID FEILER |