2313 S CLOVERDALE AVE 90016

Certificate Information: 2313 S CLOVERDALE AVE 90016

Application / Permit
20016-10000-23216
Plan Check / Job No.
B20LA16989
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT EXISITNG GARAGE INTO AN ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(C)
Permit Issued
Issued on 12/31/2020
Issuing Office
Current Status
CofO Issued on 5/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2020 APPLICANT
Assigned to Plan Check Engineer 9/22/2020 SERGIO GUTIERREZ
Corrections Issued 9/23/2020 SERGIO GUTIERREZ
Plan Check Approved 12/9/2020 AMIR DANAI
Issued 12/31/2020 APPLICANT
Building Plans Picked Up 1/12/2021 APPLICANT
CofO in Progress 5/16/2022 KATY RAMIREZ
CofO Issued 5/18/2022 ERNESTO CORRAL
Permit Finaled 5/18/2022 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 11/12/2020 THOMAS LANG
Sewer availability Cleared 11/12/2020 THOMAS LANG
Hydrant and Access approval Cleared 11/17/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 12/2/2020 THOMAS LANG

Contact Information

Contractor Jme General Construction Inc; Lic. No.: 924662-B 16274 VASQUEZ CANYON RD 7      CANYON COUNTRY, CA 91351

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/20/2021 Approved TIMOTHY BUXTON
Green Building Rough 9/29/2021 Approved KATY RAMIREZ
Interior/Exterior Lathing 9/29/2021 Partial Approval KATY RAMIREZ
Wood Frame 9/29/2021 Not Ready for Inspection KATY RAMIREZ
Wood Frame 10/29/2021 Approved KATY RAMIREZ
Insulation 11/10/2021 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 11/17/2021 Conditional Approval DARRYL ARNOLD
Drywall Nailing 12/1/2021 Approved DARRYL ARNOLD
Final 3/3/2022 Not Ready for Inspection KATY RAMIREZ
Green Building Final 3/3/2022 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 3/3/2022 Approved KATY RAMIREZ
Final 3/18/2022 Partial Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 3/18/2022 SGSOV Approved KATY RAMIREZ
Final 5/16/2022 OK to Issue CofO KATY RAMIREZ