1509 N BAY VIEW AVE 90744

Certificate Information: 1509 N BAY VIEW AVE 90744

Application / Permit
20016-10000-23133
Plan Check / Job No.
B20LA16927
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Convert (E) two car garage (1954SP09137, 20'x24') to Accessory Dwelling Unit Per GCS 65852.2(e)(1)(A). All work per Wood Frame Prescriptive Design.
Permit Issued
Issued on 1/13/2021
Issuing Office
Current Status
CofO Issued on 8/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 ZAW HAN
Corrections Issued 11/2/2020 ZAW HAN
Quality Review Completed 11/5/2020 TU HUA
Applicant returned to address corrections 12/14/2020 ZAW HAN
Plan Check Approved 1/7/2021 ZAW HAN
Issued 1/13/2021 APPLICANT
CofO in Progress 7/20/2021 JOHN KLARIN
CofO Issued 8/14/2021 DEROLD HAUFF
Permit Finaled 8/14/2021 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 10/28/2020 ISMAEL HERNANDEZ
Address approval Cleared 11/16/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 11/16/2020 ERIK BEASLEY
Roof/Waste drainage to street Cleared 11/16/2020 ERIK BEASLEY
Sewer availability Cleared 11/16/2020 ERIK BEASLEY
ZA Case Cleared 11/20/2020 MARITZA PRZEKOP

Contact Information

Contractor Advanced General Construction; Lic. No.: 951083-B 6545 HAZELTINE AVE # 212      VAN NUYS, CA 91401

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/15/2021 Not Ready for Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 1/15/2021 Approved JOHN KLARIN
Footing/Foundation/Slab 1/15/2021 Not Ready for Inspection JOHN KLARIN
HVAC-Rough 1/15/2021 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 1/15/2021 Partial Approval JOHN KLARIN
Underground Mechanical 1/15/2021 Partial Inspection JOHN KLARIN
Footing/Foundation/Slab 1/25/2021 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 2/4/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 2/9/2021 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 2/17/2021 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 2/26/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 3/19/2021 Approved JOHN KLARIN
PLUMBING-Rough 3/19/2021 Approved JOHN KLARIN
Gas Test 3/30/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 3/30/2021 Approved JOHN KLARIN
PLUMBING-Rough 4/1/2021 Partial Approval JOHN KLARIN
Drywall Nailing 4/7/2021 Approved JOHN KLARIN
Insulation 4/12/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/13/2021 Conditional Approval EUGENE CASSIDY
Insulation 4/20/2021 Approved SABAS ALONSO
Drywall Nailing 4/26/2021 Approved SABAS ALONSO
ELECTRICAL-Final 5/17/2021 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 5/21/2021 Approved JOHN KLARIN
Final 5/21/2021 Corrections Issued JOHN KLARIN
Green Building Final 5/21/2021 Corrections Issued JOHN KLARIN
Green Building Rough 5/21/2021 Approved JOHN KLARIN
METHANE-Final 5/21/2021 Approved JOHN KLARIN
METHANE-Rough 5/21/2021 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 5/21/2021 SGSOV Approved JOHN KLARIN
Smoke Detectors 5/21/2021 Approved JOHN KLARIN
Final 6/7/2021 Corrections Issued JOHN KLARIN
Green Building Final 6/7/2021 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 6/10/2021 Partial Approval JOHN KLARIN
Final 7/1/2021 Not Ready for Inspection JOHN KLARIN
Green Building Final 7/1/2021 Conditional Approval JOHN KLARIN
Final 7/12/2021 Corrections Issued ANSON MAGLASANG
Green Building Final 7/12/2021 Not Ready for Inspection ANSON MAGLASANG
Final 7/14/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 7/14/2021 Approved EUGENE CASSIDY
Final 7/19/2021 OK to Issue CofO JOHN KLARIN