1509 N BAY VIEW AVE 90744
Certificate Information: 1509 N BAY VIEW AVE 90744
- Application / Permit
- 20016-10000-23133
- Plan Check / Job No.
- B20LA16927
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** Convert (E) two car garage (1954SP09137, 20'x24') to Accessory Dwelling Unit Per GCS 65852.2(e)(1)(A). All work per Wood Frame Prescriptive Design.
- Permit Issued
- Issued on 1/13/2021
- Issuing Office
- Current Status
- CofO Issued on 8/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | ZAW HAN |
| Corrections Issued | 11/2/2020 | ZAW HAN |
| Quality Review Completed | 11/5/2020 | TU HUA |
| Applicant returned to address corrections | 12/14/2020 | ZAW HAN |
| Plan Check Approved | 1/7/2021 | ZAW HAN |
| Issued | 1/13/2021 | APPLICANT |
| CofO in Progress | 7/20/2021 | JOHN KLARIN |
| CofO Issued | 8/14/2021 | DEROLD HAUFF |
| Permit Finaled | 8/14/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/28/2020 | ISMAEL HERNANDEZ |
| Address approval | Cleared | 11/16/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2020 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 11/16/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 11/16/2020 | ERIK BEASLEY |
| ZA Case | Cleared | 11/20/2020 | MARITZA PRZEKOP |
Contact Information
| Contractor | Advanced General Construction; Lic. No.: 951083-B | 6545 HAZELTINE AVE # 212 VAN NUYS, CA 91401 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/15/2021 | Not Ready for Inspection | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 1/15/2021 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 1/15/2021 | Not Ready for Inspection | JOHN KLARIN |
| HVAC-Rough | 1/15/2021 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 1/15/2021 | Partial Approval | JOHN KLARIN |
| Underground Mechanical | 1/15/2021 | Partial Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 1/25/2021 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 2/4/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 2/9/2021 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/17/2021 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 2/26/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 3/19/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 3/19/2021 | Approved | JOHN KLARIN |
| Gas Test | 3/30/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 3/30/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 4/1/2021 | Partial Approval | JOHN KLARIN |
| Drywall Nailing | 4/7/2021 | Approved | JOHN KLARIN |
| Insulation | 4/12/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/13/2021 | Conditional Approval | EUGENE CASSIDY |
| Insulation | 4/20/2021 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/26/2021 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 5/17/2021 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 5/21/2021 | Approved | JOHN KLARIN |
| Final | 5/21/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 5/21/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 5/21/2021 | Approved | JOHN KLARIN |
| METHANE-Final | 5/21/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 5/21/2021 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 5/21/2021 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 5/21/2021 | Approved | JOHN KLARIN |
| Final | 6/7/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 6/7/2021 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 6/10/2021 | Partial Approval | JOHN KLARIN |
| Final | 7/1/2021 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 7/1/2021 | Conditional Approval | JOHN KLARIN |
| Final | 7/12/2021 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 7/12/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 7/14/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/14/2021 | Approved | EUGENE CASSIDY |
| Final | 7/19/2021 | OK to Issue CofO | JOHN KLARIN |