4401 W WILSHIRE BLVD 90010

Certificate Information: 4401 W WILSHIRE BLVD 90010

Application / Permit
20016-10000-23119
Plan Check / Job No.
B20LA16922
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
TENANT IMPROVEMENT FOR EXISTING 5-STORY COMMERCIAL BUILDING. RE-STRIPING OF PARKING FOR 2 ACCESSIBLE PARKING STALLS. NO CHANGE OF USE. NO CHANGE IN NUMBER OF PARKING STALLS. NO STRUCTURAL WORK ALLOWED ON THIS PERMIT FOR THIS NON-DUCTILE CONCRETE BUILDING UNLESS SHOWN IN THIS PERMITTED TENANT IMPROVEMENT PLAN. SUBMITTAL FEES COLLECTED UNDER PERMIT #20016-10000-06834 SUBMITTAL. NFPA-13 FIRE SPRINKLER REQUIRED.
Permit Issued
Issued on 6/9/2023
Issuing Office
Metro
Current Status
Permit Finaled on 4/17/2025

Permit Application Status History

Submitted 9/17/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 ERWIN PASCUA
Corrections Issued 10/5/2020 ERWIN PASCUA
Quality Review Completed 10/5/2020 CHARLES CHANG
Applicant returned to address corrections 12/15/2020 ERWIN PASCUA
Applicant returned to address corrections 12/16/2020 ERWIN PASCUA
Applicant returned to address corrections 3/18/2021 ERWIN PASCUA
Applicant returned to address corrections 12/1/2021 ERWIN PASCUA
Applicant returned to address corrections 12/21/2021 ERWIN PASCUA
Applicant returned to address corrections 12/22/2021 ERWIN PASCUA
Disabled Access Plans Picked Up 1/31/2022 APPLICANT
Green Plans Picked Up 1/31/2022 APPLICANT
Plan Check Approved 3/16/2022 TSE MING HUANG
Building Plans Picked Up 3/23/2022 APPLICANT
Plan Check Approved 6/9/2023 TSE MING HUANG
Issued 6/9/2023 APPLICANT
Permit Finaled 4/16/2025 MARTIN TAVITIAN

Permit Application Clearance Information

Green Code Cleared 12/9/2020 AARON COSTA
DAS Clearance Cleared 1/7/2021 ERWIN PASCUA
Miscellaneous Cleared 2/24/2021 CHI DANG
Specific Plan Cleared 2/24/2021 CHI DANG
ZI Cleared 2/24/2021 CHI DANG
Fire Marshal Fire Life Safety Cleared 12/20/2021 MENOA AGHAJANI
Building over 36-ft Cleared 12/22/2021 CALOSHA APPROVED
Metro Rail approval Cleared 12/22/2021 ERWIN PASCUA

Contact Information

Architect Lu,, Johnny C; Lic. No.: C30396 17620 FITCH AVE. SUITE 220      IRVINE, CA 92614
Contractor K T Construction Group Inc; Lic. No.: 1017632-B 18301 EAST VALLEY BLVD STE B      CITY OF INDUSTRY, CA 91744
Engineer Chen,, Duncan W.C.; Lic. No.: C81058 5690 SCHAEFER AVE #A      CHINO, CA 91710

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 12/1/2023 Partial Approval ALFREDO LOPEZ
Pre-Inspection 1/11/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 1/26/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 3/22/2024 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 3/22/2024 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 4/12/2024 Partial Approval JACOB MYERS
Insulation 5/3/2024 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 5/3/2024 Partial Approval MARTIN TAVITIAN
Drywall Nailing 5/16/2024 Partial Approval JACOB MYERS
Insulation 5/16/2024 Approved JACOB MYERS
Drywall Nailing 5/23/2024 Partial Approval MARTIN TAVITIAN
Drywall Nailing 6/3/2024 Partial Approval MARTIN TAVITIAN
Insulation 6/12/2024 Partial Inspection JACOB MYERS
Light Gage Steel Frame 6/12/2024 Partial Approval JACOB MYERS
Drywall Nailing 6/17/2024 Partial Approval JACOB MYERS
Insulation 6/25/2024 Partial Approval JACOB MYERS
Drywall Nailing 7/1/2024 Partial Approval JACOB MYERS
Footing/Foundation/Slab 7/15/2024 Partial Approval JACOB MYERS
Light Gage Steel Frame 7/18/2024 Approved JACOB MYERS
Excavation/Setback/Form/Re-Bar 7/25/2024 Partial Approval JACOB MYERS
Drywall Nailing 7/31/2024 Partial Approval JACOB MYERS
Deputy Drilled-In Anchors 8/16/2024 Conditional Approval MICHAEL ROSENBERG
Interior/Exterior Lathing 8/16/2024 Approved JACOB MYERS
Footing/Foundation/Slab 8/19/2024 Partial Approval JACOB MYERS
Masonry Wall/Backfill 8/21/2024 Partial Approval MARTIN TAVITIAN
T-Bar Ceiling 11/5/2024 Approved MARTIN TAVITIAN
T-Bar Ceiling 11/12/2024 Partial Approval MARTIN TAVITIAN
Insulation 12/13/2024 Partial Approval MARTIN TAVITIAN
Insulation 12/20/2024 Partial Approval MARTIN TAVITIAN
Final 4/16/2025 Permit Finaled MARTIN TAVITIAN
Green Building Final 4/16/2025 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 4/16/2025 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 4/16/2025 Approved MARTIN TAVITIAN