5827 S 5TH AVE 90043

Certificate Information: 5827 S 5TH AVE 90043

Application / Permit
20016-10000-22992
Plan Check / Job No.
B20LA16846
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION AT REAR OF SFD TO EXPAND A BEDROOM ; WORK TO INCLUDE ADDITION OF BATHROOM AND WALK-IN CLOSET
Permit Issued
Issued on 9/2/2021
Issuing Office
Current Status
CofO Issued on 3/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2020 APPLICANT
Assigned to Plan Check Engineer 9/18/2020 SINA KHOSRAVI
Corrections Issued 9/24/2020 SINA KHOSRAVI
Applicant returned to address corrections 5/7/2021 ZAW HAN
Plan Check Approved 5/10/2021 ZAW HAN
Building Plans Picked Up 7/9/2021 APPLICANT
Issued 9/2/2021 APPLICANT
CofO in Progress 9/6/2022 ENRIQUE MIRELES
No Progress 2/25/2023 RICHARD STEINBACH
CofO in Progress 3/1/2023 DEROLD HAUFF
CofO Issued 3/1/2023 DEROLD HAUFF
Permit Finaled 3/1/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/19/2021 ROSA SILVA
Roof/Waste drainage to street Cleared 4/19/2021 ROSA SILVA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/12/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 10/21/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 11/3/2021 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 11/3/2021 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 11/8/2021 Partial Approval FREDDIE RIVERA
Green Building Rough 11/8/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 3/10/2022 Approved FREDDIE RIVERA
Sewer 3/10/2022 Approved FREDDIE RIVERA
Insulation 3/17/2022 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Partial Approval HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 4/18/2022 Approved ENRIQUE MIRELES
Green Building Rough 4/18/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 5/9/2022 Approved HORACE FULTZ
Insulation 5/18/2022 Corrections Issued ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 5/26/2022 Approved ENRIQUE MIRELES
Drywall Nailing 6/8/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 7/8/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/12/2022 Approved ENRIQUE MIRELES
Final 8/12/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 8/12/2022 Approved ENRIQUE MIRELES
PLUMBING-Final 8/12/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/12/2022 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 8/12/2022 Approved ENRIQUE MIRELES
Smoke Detectors 8/12/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 9/2/2022 Approved ENRIQUE MIRELES
Final 9/2/2022 OK to Issue CofO ENRIQUE MIRELES
PLUMBING-Final 9/2/2022 Approved ENRIQUE MIRELES