4630 W VENICE BLVD 90019

Certificate Information: 4630 W VENICE BLVD 90019

Application / Permit
20016-10000-22938
Plan Check / Job No.
B20LA16803
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: Install new Ordinary Moment Frame and Special Steel Cantilever Columns
Permit Issued
Issued on 1/6/2021
Issuing Office
Current Status
CofC Issued on 9/23/2021

Permit Application Status History

Submitted 9/14/2020 APPLICANT
Assigned to Plan Check Engineer 9/30/2020 HANS SANTIAGO
Corrections Issued 10/5/2020 HANS SANTIAGO
Quality Review Completed 10/6/2020 DAVID CHANG
Plan Check Approved 10/21/2020 ANDREW SANTIAGO
Issued 1/6/2021 APPLICANT
Permit Finaled-Status Void 7/7/2021 DARRYL ARNOLD
Re-Activate Permit 9/7/2021 DARRYL ARNOLD
OK for CofC 9/20/2021 ERNESTO CORRAL
OK to Issue CofC 9/20/2021 ERNESTO CORRAL
OK for CofC 9/20/2021 ERNESTO CORRAL
CofC Issued 9/23/2021 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 12/16/2020 MICHAEL SOTO

Contact Information

Contractor American Retrofitters Corp; Lic. No.: 1020382-B 15643 SHERMAN WAY STE 220      VAN NUYS, CA 91406
Engineer Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 11949 DARBY AVE      PORTER RANCH, CA 91326

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 2/8/2021 Conditional Approval MARK FERRARI
Special/Order Compliance 2/8/2021 Corrections Issued MARK FERRARI
Deputy Drilled-In Anchors 2/16/2021 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 2/16/2021 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 2/17/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 2/17/2021 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 2/18/2021 Partial Approval DARRYL ARNOLD
Deputy Reinf. Concrete 2/18/2021 Approved DARRYL ARNOLD
Deputy Reinf. Concrete 2/18/2021 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 2/18/2021 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 2/19/2021 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 2/24/2021 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 2/24/2021 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 3/2/2021 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 3/2/2021 Conditional Approval JONATHAN QUACH
Deputy Steel/Welding 3/4/2021 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 3/8/2021 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 3/8/2021 Conditional Approval DARRYL ARNOLD
Wood Frame 3/8/2021 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 3/17/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 3/18/2021 Conditional Approval MARK FERRARI
Interior/Exterior Lathing 3/19/2021 Approved DARRYL ARNOLD
Deputy Steel/Welding 5/5/2021 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 5/7/2021 Approved DARRYL ARNOLD
Deputy Steel/Welding 5/12/2021 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 5/26/2021 Conditional Approval DARRYL ARNOLD
Wood Frame 5/26/2021 Approved DARRYL ARNOLD
Interior/Exterior Lathing 6/16/2021 Conditional Approval DARRYL ARNOLD
Final 7/7/2021 Partial Inspection DARRYL ARNOLD
METHANE-Final 7/7/2021 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 7/7/2021 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 7/7/2021 Approved DARRYL ARNOLD
Final 7/12/2021 Partial Inspection DARRYL ARNOLD
Final 9/7/2021 Partial Inspection WINSTON DUNNING
Final 9/20/2021 OK for CofC ERNESTO CORRAL