Permit Issued
Issued on 3/17/2021
Issuing Office
Current Status
CofO Issued on 10/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 ARSALAN SHABESTARI
Corrections Issued 9/27/2020 ARSALAN SHABESTARI
Quality Review Completed 10/13/2020 PRANITA SHAH
Applicant returned to address corrections 11/21/2020 ARSALAN SHABESTARI
Plan Check Approved 3/12/2021 ARSALAN SHABESTARI
Issued 3/17/2021 APPLICANT
CofO in Progress 10/14/2021 ENRIQUE MIRELES
Permit Finaled 10/28/2021 DANIEL ORRANTE
CofO Issued 10/28/2021 DANIEL ORRANTE
Permit Finaled 10/28/2021 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/2/2020 OSCAR GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 11/2/2020 OSCAR GUTIERREZ
Sewer availability Cleared 11/2/2020 OSCAR GUTIERREZ
Specific Plan Cleared 11/16/2020 PEDRO AYALA
Construction near power lines Cleared 2/5/2021 RIDWAN HARDY
Construction within easement Cleared 2/5/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/1/2021 Corrections Issued ENRIQUE MIRELES
Underground Mechanical 4/6/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 4/12/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/14/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 5/14/2021 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 5/14/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 5/14/2021 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 5/18/2021 Approved ENRIQUE MIRELES
HVAC-Rough 5/18/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 5/18/2021 Approved ENRIQUE MIRELES
Insulation 5/26/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 5/27/2021 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Approved ENRIQUE MIRELES
Drywall Nailing 6/10/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 6/11/2021 Partial Approval ADAM ESCOTO
Interior/Exterior Lathing 7/16/2021 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 8/23/2021 Partial Approval JUAN VALENZUELA
Sewer 8/23/2021 Approved JUAN VALENZUELA
ELECTRICAL-Final 10/8/2021 Approved ENRIQUE MIRELES
HVAC-Final 10/8/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 10/8/2021 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 10/14/2021 Approved ENRIQUE MIRELES
Final 10/14/2021 OK to Issue CofO ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Approved ENRIQUE MIRELES