11731 W BLIX ST 91607
Certificate Information: 11731 W BLIX ST 91607
- Application / Permit
- 20016-10000-22869
- Plan Check / Job No.
- B20LA16755
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING GARAGE/STORAGE INTO ACCESSORY DWELLING WITH TWO STORY ADDITION.
- Permit Issued
- Issued on 2/15/2022
- Issuing Office
- Current Status
- CofO Issued on 2/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 10/11/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/7/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 1/6/2022 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 1/14/2022 | APPLICANT |
| Issued | 2/15/2022 | APPLICANT |
| CofO in Progress | 7/10/2023 | JACK KARGODORIAN |
| No Progress | 1/17/2024 | JOHN COLEMAN |
| CofO in Progress | 1/17/2024 | JOHN COLEMAN |
| Permit Finaled | 2/9/2024 | RUBEN SALAS |
| CofO Issued | 2/9/2024 | RUBEN SALAS |
| Permit Finaled | 2/9/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 11/17/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 7/8/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/11/2021 | GABRIEL ROBLES |
| Specific Plan | Cleared | 8/16/2021 | CORREY KITCHENS |
| Construction near power lines | Cleared | 12/11/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Fronen Construction Inc; Lic. No.: 1053555-B | 12400 VENTURA BLVD #336 STUDIO CITY, CA 91604 |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/12/2022 | Partial Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 10/20/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Underground Mechanical | 10/20/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 10/26/2022 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 10/26/2022 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 10/26/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2023 | Approved | JACK KARGODORIAN |
| Wood Frame | 1/30/2023 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 2/22/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/22/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 2/22/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 2/22/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Rough | 2/22/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 2/22/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 2/22/2023 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/28/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 2/28/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 2/28/2023 | Approved | JACK KARGODORIAN |
| Shower Pan | 3/7/2023 | Approved | JACK KARGODORIAN |
| Insulation | 3/9/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/9/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Drywall Nailing | 3/14/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/14/2023 | Partial Approval | JACK KARGODORIAN |
| Sewer | 5/18/2023 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 5/18/2023 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/24/2023 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Final | 5/24/2023 | Not Ready for Inspection | DAVID MATSON |
| Final | 5/24/2023 | Not Ready for Inspection | DAVID MATSON |
| Green Building Final | 5/24/2023 | Not Ready for Inspection | DAVID MATSON |
| HVAC-Final | 5/24/2023 | Not Ready for Inspection | DAVID MATSON |
| MERV13>=Final | 5/24/2023 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Final | 5/24/2023 | Not Ready for Inspection | DAVID MATSON |
| Reinforced Masonry Frame | 5/24/2023 | Not Ready for Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Not Ready | DAVID MATSON |
| Smoke Detectors | 5/24/2023 | Not Ready for Inspection | DAVID MATSON |
| Underground Mechanical | 5/24/2023 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 6/14/2023 | Approved | JACK KARGODORIAN |
| Final | 6/14/2023 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 6/14/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 6/14/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 6/14/2023 | Approved | JACK KARGODORIAN |
| Final | 7/3/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Final | 7/7/2023 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 1/17/2024 | Approved | JOHN COLEMAN |