1930 N TAFT AVE 90068
Certificate Information: 1930 N TAFT AVE 90068
- Application / Permit
- 20016-10000-22856
- Plan Check / Job No.
- B20LA16745
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) DETACHED GARAGE INTO ADU W/ NON LOADING BEARING INTERIOR PARTITIONS PER WFPP PER STATE LAW GCS 65852.2(E)(1)(A)
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- Issued on 4/19/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2020 | STARR CHEN |
| Corrections Issued | 9/20/2020 | STARR CHEN |
| Plan Check Approved | 3/23/2021 | TSE MING HUANG |
| Issued | 4/19/2021 | APPLICANT |
| Building Plans Picked Up | 4/23/2021 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/19/2020 | KIRK LINKLATER |
| Address approval | Cleared | 12/11/2020 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 12/11/2020 | CELINA MORENO |
| Sewer availability | Cleared | 12/11/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2020 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 1/21/2021 | JEREMY CARTER |
| City Hist. Cultural Monument | Cleared | 2/9/2021 | DEEPEAKA DHALIWAL |
| HPOZ | Cleared | 2/9/2021 | DEEPEAKA DHALIWAL |
| Historic monument | Cleared | 2/9/2021 | DEEPEAKA DHALIWAL |
Contact Information
| Contractor | Kenneth Cronon Inc; Lic. No.: 1029229-B | 10413 HAINES CYN AVE TUJUNGA, CA 91042 |
| Engineer | Samara,, Muzahim Ali; Lic. No.: C26015 | 9100 S SEPULVEDA BLVD SUITE 115 LOS ANGELES, CA 90045 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/13/2021 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/13/2021 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/23/2021 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/23/2021 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/23/2021 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/3/2021 | Approved | BRIAN SULLIVAN |
| Gas Test | 8/16/2021 | Partial Approval | BRIAN SULLIVAN |
| Sewer | 8/16/2021 | Corrections Issued | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 4/14/2022 | Partial Inspection | RUBEN SALAS |
| ELECTRICAL-Rough | 4/18/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/18/2022 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2022 | Partial Approval | BRIAN SULLIVAN |
| HVAC-Rough | 4/18/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/18/2022 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/22/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 4/22/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 4/22/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 4/22/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/22/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/22/2022 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 4/22/2022 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 5/18/2022 | Conditional Approval | JOSEPH MCGARRY |
| Sewer | 6/2/2022 | Corrections Issued | BRIAN SULLIVAN |
| Final | 2/28/2023 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 2/28/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 2/28/2023 | Approved | BRIAN SULLIVAN |