833 1/2 N JUNE ST 90038

Certificate Information: 833 1/2 N JUNE ST 90038

Application / Permit
20016-10000-22715
Plan Check / Job No.
B20LA16668
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF AN EXISTING 2-CAR GARAGE TO AN ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 11/5/2020
Issuing Office
Current Status
CofO Issued on 7/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2020 APPLICANT
Assigned to Plan Check Engineer 9/21/2020 LAWRENCE QUIRANTE
Corrections Issued 9/22/2020 LAWRENCE QUIRANTE
Plan Check Approved 10/9/2020 RICARDO RAMIREZ
Issued 11/5/2020 APPLICANT
Building Plans Picked Up 4/8/2021 APPLICANT
CofO in Progress 6/24/2021 BRIAN SULLIVAN
CofO Issued 7/28/2021 DEROLD HAUFF
Permit Finaled 7/28/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/28/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/28/2020 JEANIE LAM
Sewer availability Cleared 9/28/2020 JEANIE LAM

Contact Information

Contractor Perfitt John; Lic. No.: 1034808-B 180 SOUTH CITRUS      LOS ANGELES, CA 90036
Engineer Baich,, Brendon Chad; Lic. No.: C83347 1898 WILDROSE AVE      POMONA, CA 91767

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/25/2020 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 2/17/2021 Partial Approval BRIAN SULLIVAN
Sewer 2/26/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 3/5/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 3/31/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 3/31/2021 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2021 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 4/14/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 4/14/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/27/2021 Approved JESUS PINEDA
Pre-Inspection 4/27/2021 Approved LILIANA PORTILLO
Insulation 4/28/2021 Approved JESUS PINEDA
Pre-Inspection 4/28/2021 Approved LILIANA PORTILLO
Drywall Nailing 5/5/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/17/2021 Approved BRIAN SULLIVAN
Final 6/17/2021 Corrections Issued BRIAN SULLIVAN
Green Building Final 6/17/2021 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 6/17/2021 Approved BRIAN SULLIVAN
METHANE-Final 6/17/2021 Approved BRIAN SULLIVAN
METHANE-Rough 6/17/2021 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 6/17/2021 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 6/17/2021 Approved BRIAN SULLIVAN
Final 6/24/2021 OK to Issue CofO BRIAN SULLIVAN