2756 1/2 E MALABAR ST 90033
Certificate Information: 2756 1/2 E MALABAR ST 90033
- Application / Permit
- 20016-10000-22477
- Plan Check / Job No.
- B20LA16495
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION INTO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 4/22/2021
- Issuing Office
- Current Status
- CofO Issued on 11/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 9/22/2020 | SAMUEL GONZALEZ |
| Plan Check Approved | 3/22/2021 | FARSHAD ALIMOHAMADI |
| Issued | 4/22/2021 | APPLICANT |
| Building Plans Picked Up | 4/26/2021 | APPLICANT |
| CofO in Progress | 11/2/2021 | OSVALDO PARAMO |
| CofO in Progress | 11/2/2021 | OSVALDO PARAMO |
| Permit Finaled | 11/10/2021 | DEROLD HAUFF |
| CofO Issued | 11/10/2021 | DEROLD HAUFF |
| Permit Finaled | 11/10/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/19/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 11/19/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 1/15/2021 | JEREMY CARTER |
| Construction near power lines | Cleared | 2/16/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 5/28/2021 | Corrections Issued | OSVALDO PARAMO |
| Pre-Inspection | 6/7/2021 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/17/2021 | Approved | OSVALDO PARAMO |
| Green Building Rough | 7/13/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 7/13/2021 | Approved | OSVALDO PARAMO |
| Insulation | 7/15/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 7/27/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Drywall Nailing | 8/2/2021 | Approved | RUBEN SALAS |
| Pre-Inspection | 8/2/2021 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 8/9/2021 | Approved | OSVALDO PARAMO |
| Final | 9/20/2021 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 9/20/2021 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 9/20/2021 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 9/20/2021 | Approved | OSVALDO PARAMO |
| Final | 10/22/2021 | OK to Issue CofO | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/22/2021 | SGSOV Approved | OSVALDO PARAMO |