800 W ACADEMY ROAD 90012

Certificate Information: 800 W ACADEMY ROAD 90012

Application / Permit
20016-10000-22471
Plan Check / Job No.
B20LA16487
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT WITH ONE-STORY (8'-0" X 8'-0") ADDITION. PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 11/25/2020
Issuing Office
Current Status
Issued on 11/25/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/10/2020 APPLICANT
Assigned to Plan Check Engineer 9/16/2020 FARSHAD ALIMOHAMADI
Corrections Issued 10/6/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 11/12/2020 LUKE GONZALES
Issued 11/25/2020 APPLICANT
Building Plans Picked Up 12/17/2020 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/8/2020 JUAN ASHTON
Roof/Waste drainage to street Cleared 10/8/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 10/9/2020 JUAN ASHTON
Grading Pre-Inspection Cleared 10/21/2020 PATRICK MISCHLICH
Sewer availability Cleared 10/26/2020 JUAN ASHTON

Contact Information

Contractor Builder Point Construction; Lic. No.: 1059885-B 11445 PARAMOUNT BLVD SUITE H      DOWNEY, CA 90241
Engineer Vega,, Cayetano Gonzalez; Lic. No.: C43117 9234 STAMPS AVE      DOWNEY, CA 90240

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/5/2021 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 1/11/2021 Approved RUBEN SALAS
Underground Mechanical 1/11/2021 Not Ready for Inspection RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 2/16/2021 Approved OSVALDO PARAMO
ELECTRICAL-Rough 3/15/2021 Approved OSVALDO PARAMO
HVAC-Rough 3/15/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 3/17/2021 Approved OSVALDO PARAMO
Green Building Rough 3/17/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 3/17/2021 Approved OSVALDO PARAMO
Insulation 3/19/2021 Approved OSVALDO PARAMO
Drywall Nailing 3/23/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/23/2021 Approved OSVALDO PARAMO
Shower Pan 3/23/2021 Approved OSVALDO PARAMO
Final 6/10/2021 Not Ready for Inspection OSVALDO PARAMO
Green Building Final 6/10/2021 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 6/10/2021 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 6/10/2021 Not Ready for Inspection OSVALDO PARAMO
Final 6/16/2021 Corrections Issued OSVALDO PARAMO