354 N ALTA VISTA BLVD 90036
Certificate Information: 354 N ALTA VISTA BLVD 90036
- Application / Permit
- 20016-10000-22358
- Plan Check / Job No.
- B20LA16416
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REDUCE THE SIZE OF THE EXISTING DETACHED GARAGE AND CONVERT IT INTO AN ACCESSORY DWELLING UNIT PER 12.22.A.33(c) AND (d). BUILDING SHALL BE EQUIPPED WITH NFPA-13D FIRE SPRINKLER THRU-OUT. 2 OF 2
- Permit Issued
- Issued on 4/7/2021
- Issuing Office
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | JOHNNY WU |
| Corrections Issued | 10/9/2020 | JOHNNY WU |
| Quality Review Completed | 10/15/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 10/19/2020 | APPLICANT |
| Applicant returned to address corrections | 1/20/2021 | JOHNNY WU |
| Applicant returned to address corrections | 3/4/2021 | JOHNNY WU |
| Applicant returned to address corrections | 3/12/2021 | JOHNNY WU |
| Plan Check Approved | 4/7/2021 | JOHNNY WU |
| Issued | 4/7/2021 | APPLICANT |
| CofO in Progress | 10/7/2022 | MICHAEL LEWIS |
| Permit Finaled | 10/15/2022 | DEROLD HAUFF |
| CofO Issued | 10/15/2022 | DEROLD HAUFF |
| Permit Finaled | 10/15/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/3/2020 | WALTER RAMIREZ |
| Address approval | Cleared | 2/5/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 2/5/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 2/5/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 3/5/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/16/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 8/16/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 8/16/2021 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 8/16/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/8/2021 | Approved | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 10/8/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 10/8/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/8/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/8/2021 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 10/8/2021 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 10/8/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/28/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/28/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/28/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/28/2021 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 10/28/2021 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 10/28/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 1/6/2022 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 1/6/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 2/1/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/1/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 2/11/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/11/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/16/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 10/3/2022 | Approved | MICHAEL LEWIS |
| Final | 10/3/2022 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 10/3/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 10/3/2022 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 10/3/2022 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 10/3/2022 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 10/3/2022 | Approved | MICHAEL LEWIS |
| Final | 10/6/2022 | OK to Issue CofO | MICHAEL LEWIS |