3010 S DELL AVE 90291

Certificate Information: 3010 S DELL AVE 90291

Application / Permit
20016-10000-22333
Plan Check / Job No.
B20LA16399
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING GARAGE TO BE CONVERTED TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 11/19/2021
Issuing Office
Current Status
CofO Issued on 12/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2020 APPLICANT
Assigned to Plan Check Engineer 9/11/2020 TSE MING HUANG
Corrections Issued 9/12/2020 TSE MING HUANG
Applicant returned to address corrections 11/3/2021 GEORGE ALVAREZ
Plan Check Approved 11/8/2021 GEORGE ALVAREZ
Issued 11/19/2021 APPLICANT
Building Plans Picked Up 12/1/2021 APPLICANT
CofO in Progress 11/23/2022 DAVID FEILER
Permit Finaled 12/1/2022 DANIEL ORRANTE
CofO Issued 12/1/2022 DANIEL ORRANTE
Permit Finaled 12/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/1/2020 SAUL GARCIA
Sewer availability Cleared 10/1/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 10/2/2020 SAUL GARCIA
Specific Plan Cleared 10/6/2020 FREDDY GARCIA
Specific Plan Cleared 10/6/2020 FREDDY GARCIA
Hydrant and Access approval Cleared 1/7/2021 MATTHEW CRAIG
Construction near power lines Cleared 3/1/2021 RIDWAN HARDY
Construction within easement Cleared 3/1/2021 RIDWAN HARDY
Coastal Zone Cleared 10/19/2021 DANIEL CORONADO
Specific Plan Cleared 10/19/2021 DANIEL CORONADO

Contact Information

Architect O'Neill,, Brian Stephen; Lic. No.: C30195 691 WONDER VIEW DRIVE      CALABASAS, CA 91302
Contractor Medina Construction Co; Lic. No.: 836012-B 1068 E BENBOW ST      COVINA, CA 91724
Engineer Resnick,, Bruce Daniel; Lic. No.: S3293 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/3/2022 Partial Inspection DAVID FEILER
PLUMBING-Rough 5/19/2022 Corrections Issued JESUS RODRIGUEZ
Sewer 5/19/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 5/19/2022 Partial Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 6/7/2022 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 6/10/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 7/8/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 7/8/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 7/20/2022 Partial Approval DAVID FEILER
Green Building Rough 7/20/2022 Approved DAVID FEILER
METHANE-Rough 7/20/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 8/1/2022 Approved STEPHANIE SWANSON
Insulation 8/1/2022 Approved STEPHANIE SWANSON
Drywall Nailing 8/5/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 8/5/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 8/5/2022 Approved STEPHANIE SWANSON
Shower Pan 8/5/2022 Approved STEPHANIE SWANSON
Final 10/6/2022 Corrections Issued DAVID FEILER
Green Building Final 10/6/2022 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 10/6/2022 Approved DAVID FEILER
Final 11/2/2022 Partial Approval DAVID FEILER
Final 11/23/2022 OK to Issue CofO DAVID FEILER