149 3/4 W 74TH ST 90003
Certificate Information: 149 3/4 W 74TH ST 90003
- Application / Permit
- 20016-10000-22329
- Plan Check / Job No.
- B20LA16390
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ATTACHED GARAGE CONVERSION INTO ADU; 400 SQFT IN DUPLEX
- Permit Issued
- Issued on 1/6/2021
- Issuing Office
- Current Status
- CofO Issued on 3/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2020 | ADAM HEGAZI |
| Corrections Issued | 9/30/2020 | ADAM HEGAZI |
| Applicant returned to address corrections | 10/20/2020 | SINA KHOSRAVI |
| Plan Check Approved | 12/8/2020 | AMIR DANAI |
| Issued | 1/6/2021 | APPLICANT |
| Building Plans Picked Up | 1/7/2021 | APPLICANT |
| CofO in Progress | 2/26/2026 | JOHN QUINTANILLA |
| No Progress | 2/26/2026 | MICHAEL LEWIS |
| CofO in Progress | 2/26/2026 | MICHAEL LEWIS |
| Permit Finaled | 3/19/2026 | DEROLD HAUFF |
| CofO Issued | 3/19/2026 | DEROLD HAUFF |
| Permit Finaled | 3/19/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2020 | JAMES KHO |
| Sewer availability | Cleared | 10/13/2020 | JAMES KHO |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2020 | JAMES KHO |
| Tenant Habitability Plan | Cleared | 12/28/2020 | ISMAEL HERNANDEZ |
Contact Information
| Architect | Garcia,, Hugo; Lic. No.: C33055 | 6429 DOS RIOS ROAD DOWNEY, CA 90240 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/1/2022 | No Access for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/7/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/15/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 3/15/2022 | Corrections Issued | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 3/31/2022 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Rough | 3/31/2022 | Not Ready for Inspection | HORACE FULTZ |
| Interior/Exterior Lathing | 3/31/2022 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 3/31/2022 | Corrections Issued | HORACE FULTZ |
| Interior/Exterior Lathing | 12/1/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 12/1/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/30/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/30/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 12/30/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 12/30/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 12/30/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 2/17/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 2/17/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 5/25/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 5/25/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/25/2023 | Approved | MICHAEL LEWIS |
| Insulation | 6/26/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 6/26/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 7/2/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/2/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 8/7/2025 | Approved | JOHN QUINTANILLA |
| Final | 8/7/2025 | Conditional Approval | JOHN QUINTANILLA |
| Green Building Final | 8/7/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Final | 8/7/2025 | Partial Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 8/7/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 8/7/2025 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 8/14/2025 | Approved | JOHN QUINTANILLA |
| Final | 2/25/2026 | OK to Issue CofO | JOHN QUINTANILLA |