3000 W EXPOSITION PL 90018

Certificate Information: 3000 W EXPOSITION PL 90018

Application / Permit
20016-10000-22243
Plan Check / Job No.
B20LA16309
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION TO A.D.U. PER STATE LAW.
Permit Issued
Issued on 8/11/2021
Issuing Office
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2020 APPLICANT
Assigned to Plan Check Engineer 9/16/2020 JESSE JIMENEZ
Corrections Issued 9/17/2020 JESSE JIMENEZ
Applicant returned to address corrections 10/30/2020 AMIR DANAI
Applicant returned to address corrections 12/10/2020 RICARDO RAMIREZ
Applicant returned to address corrections 4/27/2021 RAHEL BEYENE
Applicant returned to address corrections 5/12/2021 RAHEL BEYENE
Applicant returned to address corrections 6/17/2021 RAHEL BEYENE
Building Plans Picked Up 6/21/2021 APPLICANT
Applicant returned to address corrections 7/19/2021 LAWRENCE QUIRANTE
Plan Check Approved 8/11/2021 LAWRENCE QUIRANTE
Issued 8/11/2021 APPLICANT
CofO in Progress 4/26/2022 ANTHONY EGSON
Permit Finaled 4/28/2022 DEROLD HAUFF
CofO Issued 4/28/2022 DEROLD HAUFF
Permit Finaled 4/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/30/2020 CELINA MORENO
Sewer availability Cleared 12/30/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/5/2021 CELINA MORENO
Permit Cleared 1/5/2021 CELINA MORENO
Hydrant and Access approval Cleared 3/10/2021 ROBERT DUFF
Tenant Habitability Plan Cleared 4/12/2021 ISMAEL HERNANDEZ
Construction near power lines Cleared 6/21/2021 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/16/2021 Partial Inspection DAVID FEILER
Wood Frame 9/16/2021 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 9/29/2021 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 9/29/2021 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 10/13/2021 Approved ALIZAH MAYAGOITIA
Sewer 10/13/2021 Approved ALIZAH MAYAGOITIA
Special/Order Compliance 10/13/2021 Partial Inspection ADAM ESCOTO
BUILDING-Rough-Frame 11/4/2021 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 11/4/2021 Not Ready for Inspection ANTHONY EGSON
FLOOD-Proofing Certificate 11/4/2021 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 11/4/2021 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 11/4/2021 Partial Inspection ANTHONY EGSON
Wood Frame 11/4/2021 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 11/29/2021 Conditional Approval ADAM ESCOTO
ELECTRICAL-Rough 11/29/2021 Approved ADAM ESCOTO
FLOOD-Proofing Certificate 11/29/2021 Approved ADAM ESCOTO
Green Building Rough 11/29/2021 Not Ready for Inspection ADAM ESCOTO
HVAC-Rough 11/29/2021 Approved ADAM ESCOTO
PLUMBING-Rough 11/29/2021 Approved ADAM ESCOTO
BUILDING-Rough-Frame 12/2/2021 Partial Inspection AMY COLIN
Green Building Rough 12/2/2021 Approved AMY COLIN
Insulation 12/2/2021 Approved AMY COLIN
Interior/Exterior Lathing 12/2/2021 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Approved ANTHONY EGSON
Drywall Nailing 12/15/2021 Corrections Issued SHAVONNE ESPINOZA
Drywall Nailing 12/16/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 12/16/2021 Not Ready for Inspection ADAM ESCOTO
BUILDING-Rough-Frame 1/13/2022 Approved AMY COLIN
ELECTRICAL-Final 1/13/2022 Partial Approval AMY COLIN
HVAC-Final 1/13/2022 Approved AMY COLIN
Interior/Exterior Lathing 1/13/2022 Corrections Issued AMY COLIN
PLUMBING-Final 1/13/2022 Corrections Issued AMY COLIN
Smoke Detectors 1/13/2022 Approved AMY COLIN
ELECTRICAL-Final 1/19/2022 Approved ADAM ESCOTO
Gas Test 1/19/2022 Approved ADAM ESCOTO
Interior/Exterior Lathing 1/19/2022 Approved ADAM ESCOTO
PLUMBING-Final 1/19/2022 Approved ADAM ESCOTO
Shower Pan 1/19/2022 Approved ADAM ESCOTO
Final 1/28/2022 Conditional Approval HORACE FULTZ
Green Building Final 1/28/2022 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 1/28/2022 SGSOV Approved HORACE FULTZ
ELECTRICAL-Final 3/14/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 3/16/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 3/18/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 3/23/2022 Corrections Issued HORACE FULTZ
ELECTRICAL-Final 4/6/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 4/11/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 4/15/2022 Approved ANTHONY EGSON