11498 W LA MAIDA ST 91601
Certificate Information: 11498 W LA MAIDA ST 91601
- Application / Permit
- 20016-10000-22227
- Plan Check / Job No.
- B20LA16289
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION TO ADU
- Permit Issued
- Issued on 10/28/2020
- Issuing Office
- Current Status
- CofO Issued on 3/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2020 | ADAM HEGAZI |
| Corrections Issued | 9/14/2020 | ADAM HEGAZI |
| Applicant returned to address corrections | 10/22/2020 | RACHEL BEYENE |
| Plan Check Approved | 10/23/2020 | RAHEL BEYENE |
| Issued | 10/28/2020 | APPLICANT |
| Building Plans Picked Up | 10/29/2020 | APPLICANT |
| CofO in Progress | 3/4/2021 | DANIEL ORRANTE |
| CofO Issued | 3/4/2021 | MICHAEL SMITH |
| Permit Finaled | 3/4/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/23/2020 | CECILIO NAVARRO |
| Specific Plan | Cleared | 10/14/2020 | ERIN NASH |
Contact Information
| Contractor | K G Constructions Solutions Usa Inc; Lic. No.: 887210-B | 12439 MAGNOLIA BLVD STE 230 VALLEY VILLAGE, CA 91607 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/4/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 11/4/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 11/4/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 11/6/2020 | Conditional Approval | DANIEL ORRANTE |
| ELECTRICAL-Rough | 11/12/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/12/2020 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 11/12/2020 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 11/12/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 11/13/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 11/13/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 11/16/2020 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/19/2020 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 11/19/2020 | No Access for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/30/2020 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 11/30/2020 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 11/30/2020 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/10/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2020 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 12/10/2020 | Partial Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 12/16/2020 | Conditional Approval | THOMAS FINNILA |
| HVAC-Rough | 12/16/2020 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/16/2020 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 12/16/2020 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 12/17/2020 | Approved | MATTHEW NELSON |
| HVAC-Rough | 12/17/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/22/2020 | Partial Approval | BEAU COLLINS |
| Green Building Rough | 12/22/2020 | Approved | BEAU COLLINS |
| Interior/Exterior Lathing | 12/22/2020 | Partial Approval | BEAU COLLINS |
| MERV13>=Rough | 12/22/2020 | Approved | BEAU COLLINS |
| PLUMBING-Rough | 12/22/2020 | Approved | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2020 | Approved | THOMAS FINNILA |
| Insulation | 12/24/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/24/2020 | Approved | THOMAS FINNILA |
| Drywall Nailing | 12/29/2020 | Approved | THOMAS FINNILA |
| Shower Pan | 1/13/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/28/2021 | Approved | THOMAS FINNILA |
| Final | 1/28/2021 | Corrections Issued | THOMAS FINNILA |
| MERV13>=Final | 1/28/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 1/28/2021 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 1/28/2021 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 2/5/2021 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 2/5/2021 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/5/2021 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 2/5/2021 | Approved | THOMAS FINNILA |