8456 N TUNNEY AVE 91324

Certificate Information: 8456 N TUNNEY AVE 91324

Application / Permit
20016-10000-22215
Plan Check / Job No.
B20LA16283
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. CONVERT EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 12/22/2020
Issuing Office
Current Status
CofO Issued on 4/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 MICHAEL LOPEZ
Corrections Issued 10/8/2020 MICHAEL LOPEZ
Quality Review Completed 10/13/2020 PRANITA SHAH
Applicant returned to address corrections 11/17/2020 MICHAEL LOPEZ
Applicant returned to address corrections 12/4/2020 MICHAEL LOPEZ
Plan Check Approved 12/17/2020 MICHAEL LOPEZ
Issued 12/22/2020 APPLICANT
CofO in Progress 4/15/2021 JEFFREY PARD
CofO Issued 4/30/2021 JOHN JANSON
Permit Finaled 4/30/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/14/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/14/2020 ADRIAN CASTRO
Sewer availability Cleared 10/14/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Santos,, Michael Fernandez; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/29/2020 Partial Approval JEFFREY PARD
Pre-Inspection 1/7/2021 Not Ready for Inspection JEFFREY PARD
Deputy Drilled-In Anchors 1/26/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 2/2/2021 Not Ready for Inspection JEFFREY PARD
Excavation/Setback/Form/Re-Bar 2/2/2021 Approved JEFFREY PARD
Gas Test 2/2/2021 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 2/2/2021 Not Ready for Inspection JEFFREY PARD
Rough-Elec/Plmb/HVAC 2/2/2021 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 2/11/2021 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 2/11/2021 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 2/11/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/11/2021 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/16/2021 Not Ready for Inspection JEFFREY PARD
Green Building Rough 2/16/2021 Not Ready for Inspection JEFFREY PARD
Rough-Elec/Plmb/HVAC 2/16/2021 Partial Approval JEFFREY PARD
Insulation 2/18/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Drywall Nailing 2/23/2021 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 2/23/2021 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 2/23/2021 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 2/23/2021 Not Ready for Inspection JEFFREY PARD
Rough-Elec/Plmb/HVAC 2/23/2021 Not Ready for Inspection JEFFREY PARD
Deputy Drilled-In Anchors 2/24/2021 No Access for Inspection JEFFREY PARD
BUILDING-Rough-Frame 2/26/2021 Approved JEFFREY PARD
Green Building Rough 2/26/2021 Approved JEFFREY PARD
Insulation 2/26/2021 Approved JEFFREY PARD
Interior/Exterior Lathing 2/26/2021 Order to Comply Issued JEFFREY PARD
PLUMBING-Rough 2/26/2021 Approved JEFFREY PARD
Drywall Nailing 3/2/2021 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 3/3/2021 Approved JEFFREY PARD
Final 3/25/2021 Not Ready for Inspection JEFFREY PARD
Green Building Final 3/25/2021 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Approved JEFFREY PARD
Smoke Detectors 3/25/2021 Approved JEFFREY PARD
Final 4/1/2021 Not Ready for Inspection JEFFREY PARD
Green Building Final 4/1/2021 Not Ready for Inspection JEFFREY PARD
Final 4/15/2021 OK to Issue CofO JEFFREY PARD
Green Building Final 4/15/2021 Approved JEFFREY PARD